up_reraStatus: Completed
CASE ID: 0901126015442020

Appellant / Complainant

Paarth Infrabuild Pvt. Ltd.

VS

Respondent

Hari Ram Lal

Developer Firm

paarth infrabuild pvt. ltd.

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Jurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

22 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126015442020 by Paarth Infrabuild Pvt. Ltd. against Hari Ram Lal before up_rera.

Jurisdiction & Maintainability
2
Stage 108/03/2022

Hearing

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be released by the Regulatory Authority following due diligence to ensure proper distribution between the promoter and the allottee.

3
Stage 204/01/2022

Hearing

The Tribunal granted the applicant 10 days to ensure complete compliance with Section 43(5) of the Act and deposit any remaining balance via the e-portal following an initial deposit of Rs. 10,678/-.

4
Stage 320/12/2021

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to the illness of their Senior Advocate and rescheduled the hearing for January 4, 2022.

5
Stage 430/11/2021

Hearing

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the applicant to comply with the provisions of Section 43(5) of the Act.

6
Stage 511/11/2021

Further Hearing

The Tribunal refers to a previous order dated 11.11.2020 and schedules the matter for a hearing on 30.11.2021.

7
Stage 608/10/2021

Further Hearing

The Tribunal reprimanded the appellant's counsel for seeking an adjournment via email rather than through formal appearance and adjourned the matter to 11.11.2021.

8
Stage 722/04/2021

Compliance of section 43(5)

No text available.

9
Stage 805/04/2021

Compliance of section 43(5)

No text available.

10
Stage 915/03/2021

Final Hearing

The Tribunal issued notice to respondent numbers 3 and 4, permitting the appellant to serve them via dasti summons and directing the filing of a reply to the objections of respondents 1 and 2.

11
Stage 1024/02/2021

Compliance of section 43(5)

The matter was adjourned due to an advocate strike called by the Oudh Bar Association, with the defective appeal rescheduled for hearing on 15.03.2021.

12
Stage 1122/02/2021

For Order

The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the hearing for 24.02.2021.

13
Stage 1203/02/2021

For Order

The Tribunal directed the applicant to comply with Section 43(5) of the Act and file a reply to the respondent's objections within one week, noting that the applicant appeared to be unnecessarily delaying the matter. The case was adjourned to 22.02.2021 with a strict directive that no further adjournments will be granted.

14
Stage 1318/01/2021

Admission

The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and directed that the reply be emailed to the respondent and uploaded to the e-portal.

15
Stage 1415/12/2020

Admission

No text available.

16
Stage 1520/11/2020

Admission

No text available.

17
Stage 16Interim Order

Tribunal Order #0901126015442020-08-10-2021

The Tribunal reprimanded the appellant's counsel for seeking an adjournment via email rather than through formal appearance and adjourned the matter to 11.11.2021.

18
Stage 17Interim Order

Tribunal Order #0901126015442020-03-02-2021

The Tribunal directed the applicant to comply with Section 43(5) of the Act and file a reply to the respondent's objections within one week, noting that the applicant appeared to be unnecessarily delaying the matter. The case was adjourned to 22.02.2021 with a strict directive that no further adjournments will be granted.

19
Stage 18Final Ruling Order

Tribunal Order #0901126015442020-08-03-2022

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be released by the Regulatory Authority following due diligence to ensure proper distribution between the promoter and the allottee.

20
Stage 19Interim Order

Tribunal Order #0901126015442020-04-01-2022

The Tribunal granted the applicant 10 days to ensure complete compliance with Section 43(5) of the Act and deposit any remaining balance via the e-portal following an initial deposit of Rs. 10,678/-.

21
Stage 20Interim Order

Tribunal Order #0901126015442020-30-11-2021

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the applicant to comply with the provisions of Section 43(5) of the Act.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be released by the Regulatory Authority following due diligence to ensure proper distribution between the promoter and the allottee. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be released by the Regulatory Authority following due diligence to ensure proper distribution between the promoter and the allottee.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajiv Shukla
  • Rahul Shukla

Respondent Advocate(s)

  • In Person

Official RERA Tribunal Orders (5)

INTERIM_ORDEROrder ID: 0901126015442020-08-10-2021

The Tribunal reprimanded the appellant's counsel for seeking an adjournment via email rather than through formal appearance and adjourned the matter to 11.11.2021.

INTERIM_ORDEROrder ID: 0901126015442020-03-02-2021

The Tribunal directed the applicant to comply with Section 43(5) of the Act and file a reply to the respondent's objections within one week, noting that the applicant appeared to be unnecessarily delaying the matter. The case was adjourned to 22.02.2021 with a strict directive that no further adjournments will be granted.

FINAL_ORDEROrder ID: 0901126015442020-08-03-2022

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be released by the Regulatory Authority following due diligence to ensure proper distribution between the promoter and the allottee.

INTERIM_ORDEROrder ID: 0901126015442020-04-01-2022

The Tribunal granted the applicant 10 days to ensure complete compliance with Section 43(5) of the Act and deposit any remaining balance via the e-portal following an initial deposit of Rs. 10,678/-.

INTERIM_ORDEROrder ID: 0901126015442020-30-11-2021

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the applicant to comply with the provisions of Section 43(5) of the Act.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paarth infrabuild pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →