CASE ID: 0901126016312020

Appellant / Complainant

Paarth Infrabuild Pvt. Ltd.

VS

Respondent

Shashank Agarwal

Developer Firm

paarth infrabuild pvt. ltd.

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Jurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

22 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126016312020 by Paarth Infrabuild Pvt. Ltd. against Shashank Agarwal before up_rera.

Jurisdiction & Maintainability
2
Stage 108/03/2022

Hearing

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority for distribution to the allottee or return to the promoter after due diligence.

3
Stage 204/01/2022

Hearing

The Tribunal noted the deposit of Rs. 3,84,000/- and directed the Registry to verify compliance with Section 43(5) of the Act, while instructing the applicant to rectify any deficiencies before the next hearing on 25.01.2022.

4
Stage 320/12/2021

Hearing

The Tribunal granted an adjournment requested by the counsel for the applicant due to the ill health of the Senior Advocate and rescheduled the hearing to 04.01.2022.

5
Stage 430/11/2021

Hearing

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the applicant to comply with the provisions of Section 43(5) of the Act.

6
Stage 511/11/2021

Further Hearing

The Tribunal has scheduled the hearing for this appeal to take place on November 30, 2021.

7
Stage 608/10/2021

Further Hearing

The Tribunal issued a warning to the appellant's counsel against seeking adjournments via email and subsequently adjourned the matter to 11.11.2021 due to the unavailability of the Senior Advocate.

8
Stage 722/04/2021

Compliance of section 43(5)

No text available.

9
Stage 805/04/2021

Compliance of section 43(5)

No text available.

10
Stage 915/03/2021

Further Hearing

No text available.

11
Stage 1024/02/2021

Defect Removal

The tribunal adjourned the defective appeal due to advocates abstaining from work on the call of the Oudh Bar Association and rescheduled the matter for 15.03.2021.

12
Stage 1122/02/2021

Compliance of section 43(5)

The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the case for further hearing on 24.02.2021.

13
Stage 1219/02/2021

For Order

No text available.

14
Stage 1301/02/2021

For Order

The Tribunal granted a request for adjournment made by the appellant's counsel due to them being out of station and rescheduled the case for 19.02.2021.

15
Stage 1411/01/2021

Admission

No text available.

16
Stage 1515/12/2020

Admission

No text available.

17
Stage 1620/11/2020

Admission

No text available.

18
Stage 17Final Ruling Order

Tribunal Order #0901126016312020-08-03-2022

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority for distribution to the allottee or return to the promoter after due diligence.

19
Stage 18Interim Order

Tribunal Order #0901126016312020-30-11-2021

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the applicant to comply with the provisions of Section 43(5) of the Act.

20
Stage 19Interim Order

Tribunal Order #0901126016312020-08-10-2021

The Tribunal issued a warning to the appellant's counsel against seeking adjournments via email and subsequently adjourned the matter to 11.11.2021 due to the unavailability of the Senior Advocate.

21
Stage 20Interim Order

Tribunal Order #0901126016312020-04-01-2022

The Tribunal noted the deposit of Rs. 3,84,000/- and directed the Registry to verify compliance with Section 43(5) of the Act, while instructing the applicant to rectify any deficiencies before the next hearing on 25.01.2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority for distribution to the allottee or return to the promoter after due diligence. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority for distribution to the allottee or return to the promoter after due diligence.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajiv Shukla
  • Rahul Shukla

Respondent Advocate(s)

  • In Person
  • Anurag Arora

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126016312020-08-03-2022

The Tribunal allowed the appellant to withdraw the appeal and directed that the amount deposited under Section 43(5) of the Act be handled by the Regulatory Authority for distribution to the allottee or return to the promoter after due diligence.

INTERIM_ORDEROrder ID: 0901126016312020-30-11-2021

The Tribunal adjourned the case to 20.12.2021 and issued a final opportunity to the applicant to comply with the provisions of Section 43(5) of the Act.

INTERIM_ORDEROrder ID: 0901126016312020-08-10-2021

The Tribunal issued a warning to the appellant's counsel against seeking adjournments via email and subsequently adjourned the matter to 11.11.2021 due to the unavailability of the Senior Advocate.

INTERIM_ORDEROrder ID: 0901126016312020-04-01-2022

The Tribunal noted the deposit of Rs. 3,84,000/- and directed the Registry to verify compliance with Section 43(5) of the Act, while instructing the applicant to rectify any deficiencies before the next hearing on 25.01.2022.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paarth infrabuild pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →