Appellant / Complainant
Parsvnath Developers Limited
Respondent
Alok Singh
parsvnath developers limited
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126019722021 by Parsvnath Developers Limited against Alok Singh before up_rera.
Defect Removal
The appellant's counsel requested to not press the defective appeal, leading the Tribunal to dismiss the proceedings as not pressed.
Defect Removal
The Tribunal granted the appellant's counsel one week to seek instructions regarding how the promoter is aggrieved by the RERA order and scheduled the defective appeal for hearing on 05.10.2021.
Defect Removal
The Tribunal granted the appellant one week to file an application for condonation of delay and scheduled the defective appeal for hearing on 24.09.2021.
Defect Removal
The Tribunal granted the appellant a final one-week extension to remove registry defects and ensure complete compliance with Section 43(5) of the Act, warning that failure to do so by the next hearing will result in dismissal.
Tribunal Order #0901126019722021-23-03-2021
The Tribunal granted the appellant a final one-week extension to remove registry defects and ensure complete compliance with Section 43(5) of the Act, warning that failure to do so by the next hearing will result in dismissal.
Tribunal Disposal & Final Award Ruling
Dismissed as not pressed Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed as not pressed
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rajesh Chadha
Official RERA Tribunal Orders (1)
The Tribunal granted the appellant a final one-week extension to remove registry defects and ensure complete compliance with Section 43(5) of the Act, warning that failure to do so by the next hearing will result in dismissal.