Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126020572023 by Himalaya Realestate Pvt Ltd against Arun Kumar Sinha before up_rera.

2
Stage 116/04/2025

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay and dismissed the appeal due to the appellant's failure to provide a satisfactory explanation for the delay caused by their legal representative.

3
Stage 219/03/2025

Delay condonation

The Tribunal has granted a request to list the defective appeal for consideration of the application for condonation of delay and a hearing on 16.04.2025.

4
Stage 318/02/2025

Delay condonation

The Tribunal has scheduled the defective appeal for consideration regarding the application for condonation of delay on 19.03.2025, noting that no further adjournments will be granted.

5
Stage 424/01/2025

Delay condonation

The Tribunal has granted a request from the parties to list the appeal for a hearing before the regular Bench on 18.02.2025.

6
Stage 502/01/2025

For Order

The Tribunal granted the respondent one week to file objections to the appellant's interim stay application and directed both parties to submit a chart detailing the delay in handing over possession of the respective units.

7
Stage 605/11/2024

Delay condonation

No text available.

8
Stage 723/09/2024

Delay condonation

The respondent stated they are not pressing for the execution of any Recovery Certificate (R.C.) against the appellant, and the parties requested the appeal be listed for hearing on 05.11.2024.

9
Stage 820/08/2024

Delay condonation

The Tribunal refers the parties to a previously passed order dated in Appeal No. D 446/2023 for the relevant directions.

10
Stage 926/07/2024

Delay condonation

The Tribunal granted the appellant a one-week extension to file a rejoinder to the respondent's objections and scheduled the appeal for further orders/hearing on 20.08.2024.

11
Stage 1029/05/2024

Delay condonation

This is a procedural order directing the parties to refer to a previous order passed in Appeal No. D 446/2023.

12
Stage 1123/05/2024

Delay condonation

The Tribunal noted the absence of both parties and ordered the defective appeal to be listed on 29.05.2024 for consideration of the application for condonation of delay.

13
Stage 1222/04/2024

Delay condonation

The Tribunal granted an adjournment requested by the counsel for the applicant due to illness and rescheduled the appeal for hearing on 23.05.2024.

14
Stage 1318/03/2024

Delay condonation

This is a procedural order directing the parties to refer to a previously passed order dated in Appeal No. D 446/2023.

15
Stage 1415/02/2024

Delay condonation

The Tribunal granted the appellant's counsel 10 days to file a reply to the respondent's objection and scheduled the matter for hearing on 18.03.2024 regarding the application for condonation of delay.

16
Stage 1508/01/2024

Delay condonation

The Tribunal granted the applicant a final 10-day extension to file a reply to the respondent's objections and scheduled the matter for hearing on 15.02.2024.

17
Stage 1629/09/2023

Delay condonation

No text available.

18
Stage 1721/08/2023

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and grounds of appeal, with the matter scheduled for hearing on 29.09.2023.

19
Stage 1803/07/2023

Delay condonation

The Tribunal verified the appellant's compliance with Section 43(5) regarding the deposit of Rs. 2,65,557/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for 21.08.2023.

20
Stage 19Final Ruling Order

Tribunal Order #0901126020572023-16-04-2025

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay and dismissed the appeal due to the appellant's failure to provide a satisfactory explanation for the delay caused by their legal representative.

21
Stage 20Interim Order

Tribunal Order #0901126020572023-02-01-2025

The Tribunal granted the respondent one week to file objections to the appellant's interim stay application and directed both parties to submit a chart detailing the delay in handing over possession of the respective units.

22
Stage 21Interim Order

Tribunal Order #0901126020572023-03-07-2023

The Tribunal verified the appellant's compliance with Section 43(5) regarding the deposit of Rs. 2,65,557/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for 21.08.2023.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay and dismissed the appeal due to the appellant's failure to provide a satisfactory explanation for the delay caused by their legal representative. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay and dismissed the appeal due to the appellant's failure to provide a satisfactory explanation for the delay caused by their legal representative.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • N A
  • Nilaya Gupta

Respondent Advocate(s)

  • Awanitika

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126020572023-16-04-2025

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay and dismissed the appeal due to the appellant's failure to provide a satisfactory explanation for the delay caused by their legal representative.

INTERIM_ORDEROrder ID: 0901126020572023-02-01-2025

The Tribunal granted the respondent one week to file objections to the appellant's interim stay application and directed both parties to submit a chart detailing the delay in handing over possession of the respective units.

INTERIM_ORDEROrder ID: 0901126020572023-03-07-2023

The Tribunal verified the appellant's compliance with Section 43(5) regarding the deposit of Rs. 2,65,557/- and issued notice to the respondent regarding the application for condonation of delay, scheduled for 21.08.2023.

TathyaGrid RERA Intelligence AI

Need to research all rulings for himalaya realestate pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →