up_reraStatus: Completed
CASE ID: 0901126026712023

Appellant / Complainant

Rise Projects Pvt Ltd

VS

Respondent

Pooja Bansal

Developer Firm

rise projects pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

26 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126026712023 by Rise Projects Pvt Ltd against Pooja Bansal before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 107/05/2025

Delay condonation

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but ruled that the promoter is mandatory obligated to pay delay interest to the allottee at MCLR+1% from the due date of possession (excluding the COVID-19 force majeure period) until the actual offer of possession with valid OC/CC.

3
Stage 211/04/2025

Delay condonation

The court has adjourned the matter to May 7, 2025, based on a joint request from the counsel for both parties.

4
Stage 318/03/2025

Delay condonation

The appeal is adjourned to 11.04.2025 because lawyers are abstaining from judicial work following a resolution by the Real Estate Bar Association, Lucknow.

5
Stage 414/02/2025

Delay condonation

The Tribunal granted a request for adjournment and rescheduled the appeal for hearing on 18.03.2025, noting that no further adjournments will be permitted.

6
Stage 516/01/2025

Delay condonation

The parties have requested time to settle the matter amicably, and the appeal has been adjourned to 14.02.2025 for orders.

7
Stage 626/11/2024

Delay condonation

The Tribunal has adjourned the matter to 16.01.2025 to allow parties to file an affidavit regarding the project's delay, following a joint request from counsel.

8
Stage 721/10/2024

Delay condonation

The Tribunal granted an adjournment because the counsel for the appellant submitted illness slips, rescheduling the appeal for 26.11.2024.

9
Stage 811/09/2024

Delay condonation

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for orders/hearing on 21.10.2024.

10
Stage 920/08/2024

Delay condonation

The Tribunal has adjourned the appeal to 11.09.2024 for orders/hearing following a joint request from the counsel for both parties.

11
Stage 1013/08/2024

Delay condonation

The Tribunal ordered the appeal to be listed for hearing on 20.08.2024, to be heard alongside another appeal of a similar nature.

12
Stage 1115/07/2024

Delay condonation

No text available.

13
Stage 1215/05/2024

Delay condonation

No text available.

14
Stage 1315/04/2024

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the hearing for the application for condonation of delay on 15.05.2024.

15
Stage 1411/03/2024

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on 15.04.2024 regarding the application for condonation of delay.

16
Stage 1501/02/2024

Delay condonation

The Tribunal directed the appellant to file replies to the respondent's objections regarding the condonation of delay and the grounds of appeal, scheduling the next hearing for March 11, 2024.

17
Stage 1602/11/2023

Delay condonation

No text available.

18
Stage 1720/09/2023

Delay condonation

The Tribunal granted the appellant's request to issue fresh notice to the respondent regarding the application for condonation of delay, with the matter listed for hearing on 02.11.2023.

19
Stage 1816/08/2023

Delay condonation

The Tribunal ruled that the amounts recovered via the Recovery Certificate shall be treated as compliance with Section 43(5) of the Act and directed the Recovery Officer to deposit these funds in a fixed deposit for 60 days.

20
Stage 1911/08/2023

Delay condonation

The Tribunal granted a request from the appellant's counsel to list the defective appeal for orders or hearing on 16.08.2023.

21
Stage 2008/08/2023

Delay condonation

The Tribunal granted the appellant two days to submit bank statements to prove prior payment of Rs. 4,79,509/- in support of their application to waive the mandatory pre-deposit required under Section 43(5) of the Act.

22
Stage 2107/08/2023

Delay condonation

No text available.

23
Stage 22Final Ruling Order

Tribunal Order #0901126026712023-07-05-2025

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but ruled that the promoter is mandatory obligated to pay delay interest to the allottee at MCLR+1% from the due date of possession (excluding the COVID-19 force majeure period) until the actual offer of possession with valid OC/CC.

24
Stage 23Interim Order

Tribunal Order #0901126026712023-16-08-2023

The Tribunal ruled that the amounts recovered via the Recovery Certificate shall be treated as compliance with Section 43(5) of the Act and directed the Recovery Officer to deposit these funds in a fixed deposit for 60 days.

25
Stage 24Interim Order

Tribunal Order #0901126026712023-08-08-2023

The Tribunal granted the appellant two days to submit bank statements to prove prior payment of Rs. 4,79,509/- in support of their application to waive the mandatory pre-deposit required under Section 43(5) of the Act.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but ruled that the promoter is mandatory obligated to pay delay interest to the allottee at MCLR+1% from the due date of possession (excluding the COVID-19 force majeure period) until the actual offer of possession with valid OC/CC. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but ruled that the promoter is mandatory obligated to pay delay interest to the allottee at MCLR+1% from the due date of possession (excluding the COVID-19 force majeure period) until the actual offer of possession with valid OC/CC.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

w.e.f. 26.02.2020 till the date of offer of possession along with valid OC/CC (except the period from 25.03.2020 to 25.09.2020 on account of force majeure due to Covid-19 pandemic)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Siddharth Nandwani
  • Abhishek Shukla

Respondent Advocate(s)

  • Prasoon Kumar Anjor

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126026712023-07-05-2025

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but ruled that the promoter is mandatory obligated to pay delay interest to the allottee at MCLR+1% from the due date of possession (excluding the COVID-19 force majeure period) until the actual offer of possession with valid OC/CC.

INTERIM_ORDEROrder ID: 0901126026712023-16-08-2023

The Tribunal ruled that the amounts recovered via the Recovery Certificate shall be treated as compliance with Section 43(5) of the Act and directed the Recovery Officer to deposit these funds in a fixed deposit for 60 days.

INTERIM_ORDEROrder ID: 0901126026712023-08-08-2023

The Tribunal granted the appellant two days to submit bank statements to prove prior payment of Rs. 4,79,509/- in support of their application to waive the mandatory pre-deposit required under Section 43(5) of the Act.

TathyaGrid RERA Intelligence AI

Need to research all rulings for rise projects pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →