up_reraStatus: Completed
CASE ID: 0901126027362023

Appellant / Complainant

Rise Projects Pvt Ltd

VS

Respondent

Kanika Pahwa

Developer Firm

rise projects pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

27 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126027362023 by Rise Projects Pvt Ltd against Kanika Pahwa before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 107/05/2025

Delay condonation

The Appellate Tribunal set aside the Adjudicating Officer's order due to jurisdictional issues but ruled that the respondent is entitled to delay interest from 08.09.2019 until possession (excluding the COVID-19 force majeure period) at the rate of MCLR+1%.

3
Stage 211/04/2025

Delay condonation

The Tribunal has adjourned the matter to 07.05.2025 following a joint request from the learned counsel for both parties.

4
Stage 318/03/2025

Delay condonation

The appeal is adjourned to 11.04.2025 because lawyers are abstaining from judicial work following a resolution by the Real Estate Bar Association, Lucknow.

5
Stage 414/02/2025

Delay condonation

The Tribunal granted an adjournment requested by the appellant and scheduled the next hearing for March 18, 2025, noting that no further adjournments will be permitted.

6
Stage 516/01/2025

Delay condonation

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the matter for orders on 14.02.2025.

7
Stage 626/11/2024

Delay condonation

The Tribunal has adjourned the appeal to 16.01.2025 following a joint request from counsel to file an affidavit regarding the project's delay.

8
Stage 721/10/2024

Delay condonation

The Tribunal has adjourned the appeal to 26.11.2024 due to the illness of the counsels appearing for the appellant.

9
Stage 811/09/2024

Delay condonation

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for hearing/orders on 21.10.2024.

10
Stage 920/08/2024

Delay condonation

The Tribunal granted a joint request from the counsel for both parties to list the appeal for orders/hearing on 11.09.2024.

11
Stage 1007/08/2024

Delay condonation

The Tribunal granted a request by the appellant's counsel to list the defective appeal for orders or hearing on 20.08.2024.

12
Stage 1122/07/2024

Delay condonation

The Tribunal granted the appellant 7 days to file a rejoinder to the respondent's objections and scheduled the matter for hearing on 07.08.2024.

13
Stage 1222/05/2024

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objection to the condonation of delay application and directed the matter to be listed for hearing on 22.07.2024.

14
Stage 1323/04/2024

Delay condonation

The Tribunal granted the respondent a 10-day extension to file objections to the grounds of appeal and the application for condonation of delay, scheduling the next hearing for May 22, 2024.

15
Stage 1419/03/2024

Delay condonation

The Tribunal refers the parties to a previous order passed in Appeal No. D 543/2023 regarding the current matter.

16
Stage 1515/02/2024

Delay condonation

The Tribunal directed the issuance of fresh notice to the respondent via Dasti and electronic modes due to an incomplete address, scheduling the next hearing for March 19, 2024.

17
Stage 1601/02/2024

Delay condonation

The Tribunal granted the applicant one additional week to file an affidavit of service and scheduled the matter for hearing on 15.02.2024 regarding the application for condonation of delay.

18
Stage 1702/11/2023

Delay condonation

No text available.

19
Stage 1820/09/2023

Delay condonation

The Tribunal granted a request for fresh notice to be issued to the respondent regarding the application for condonation of delay and scheduled the matter for hearing on 02.11.2023.

20
Stage 1916/08/2023

Delay condonation

The Tribunal ruled that the amounts already recovered via a Recovery Certificate shall be treated as compliance with Section 43(5) of the Act, directing the Recovery Officer to deposit the funds in a fixed deposit.

21
Stage 2011/08/2023

Delay condonation

The Tribunal granted a request from the appellant's counsel to list the defective appeal for orders or hearing on 16.08.2023.

22
Stage 2108/08/2023

Delay condonation

The Tribunal addressed an application for waiver of the mandatory deposit under Section 43(5) of the Act, granting the appellant two days to submit bank statements to prove prior payment of Rs. 6,52,185 via recovery certificate.

23
Stage 2207/08/2023

Delay condonation

No text available.

24
Stage 23Interim Order

Tribunal Order #0901126027362023-16-08-2023

The Tribunal ruled that the amounts already recovered via a Recovery Certificate shall be treated as compliance with Section 43(5) of the Act, directing the Recovery Officer to deposit the funds in a fixed deposit.

25
Stage 24Final Ruling Order

Tribunal Order #0901126027362023-07-05-2025

The Appellate Tribunal set aside the Adjudicating Officer's order due to jurisdictional issues but ruled that the respondent is entitled to delay interest from 08.09.2019 until possession (excluding the COVID-19 force majeure period) at the rate of MCLR+1%.

26
Stage 25Interim Order

Tribunal Order #0901126027362023-08-08-2023

The Tribunal addressed an application for waiver of the mandatory deposit under Section 43(5) of the Act, granting the appellant two days to submit bank statements to prove prior payment of Rs. 6,52,185 via recovery certificate.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside the Adjudicating Officer's order due to jurisdictional issues but ruled that the respondent is entitled to delay interest from 08.09.2019 until possession (excluding the COVID-19 force majeure period) at the rate of MCLR+1%. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside the Adjudicating Officer's order due to jurisdictional issues but ruled that the respondent is entitled to delay interest from 08.09.2019 until possession (excluding the COVID-19 force majeure period) at the rate of MCLR+1%.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

w.e.f. 08.09.2019 till the date of offer of possession along with valid OC/CC (except the period from 25.03.2020 to 25.09.2020)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Siddharth Nandwani
  • Abhishek Shukla

Respondent Advocate(s)

  • Tushar Bahadur
  • Sachin Gupta
  • Asif Anees

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126027362023-16-08-2023

The Tribunal ruled that the amounts already recovered via a Recovery Certificate shall be treated as compliance with Section 43(5) of the Act, directing the Recovery Officer to deposit the funds in a fixed deposit.

FINAL_ORDEROrder ID: 0901126027362023-07-05-2025

The Appellate Tribunal set aside the Adjudicating Officer's order due to jurisdictional issues but ruled that the respondent is entitled to delay interest from 08.09.2019 until possession (excluding the COVID-19 force majeure period) at the rate of MCLR+1%.

INTERIM_ORDEROrder ID: 0901126027362023-08-08-2023

The Tribunal addressed an application for waiver of the mandatory deposit under Section 43(5) of the Act, granting the appellant two days to submit bank statements to prove prior payment of Rs. 6,52,185 via recovery certificate.