up_reraStatus: Completed
CASE ID: 0901126029342021

Appellant / Complainant

Jai Prakash Pandey

VS

Respondent

Paarth Infrabuild Pvt Ltd

Developer Firm

paarth infrabuild pvt ltd

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Promotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126029342021 by Jai Prakash Pandey against Paarth Infrabuild Pvt Ltd before up_rera.

Promotional Misrepresentation
2
Stage 116/05/2022

Hearing

The appeal was disposed of following an out-of-court settlement where the respondent agreed to install a video door phone and intercom facility within 30 days and provided interim access to an alternative club facility.

3
Stage 204/04/2022

Hearing

The Tribunal noted that the parties have reached a settlement and directed both parties to complete the registry of the flat and execute the conveyance/lease deed in the interim.

4
Stage 331/03/2022

Hearing

The Tribunal directed the appellant to appear in person and ordered the respondent's General Manager, Sri Satish Chandra Verma, to appear personally on the next date to facilitate a settlement regarding disputed dues and flat possession.

5
Stage 410/03/2022

Further Order

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on March 31, 2022.

6
Stage 505/01/2022

Further Order

The court noted the absence of the respondent and directed that the respondent's representative or authorized person must appear at the next hearing. The case is adjourned to 28.01.2022.

7
Stage 629/11/2021

Further Order

The Tribunal allowed the limitation application, condoning a 54-day delay in filing the appeal based on Supreme Court precedents, and directed the registry to convert the defective appeal into a regular appeal.

8
Stage 729/10/2021

Delay condonation

The Tribunal directed the respondent to file an objection against the appellant's limitation application within one week and scheduled the matter for 29.11.2021 to dispose of said application.

9
Stage 829/09/2021

Delay condonation

The Tribunal issued a warning to the respondent's counsel for failing to file a vakalatnama and objections as promised, granting a final 10-day extension for filing objections to the condonation of delay application and grounds of appeal.

10
Stage 907/09/2021

Delay condonation

The Tribunal granted the respondent ten days to file objections to the application for condonation of delay and directed the parties to exchange replies via email before the next hearing on 29.09.2021.

11
Stage 1013/08/2021

Delay condonation

The Tribunal issued notice on the application for condonation of delay and directed the parties to exchange pleadings via email and upload them to the e-portal before the next hearing on 07.09.2021.

12
Stage 11Interim Order

Tribunal Order #0901126029342021-29-09-2021

The Tribunal issued a warning to the respondent's counsel for failing to file a vakalatnama and objections as promised, granting a final 10-day extension for filing objections to the condonation of delay application and grounds of appeal.

13
Stage 12Final Ruling Order

Tribunal Order #0901126029342021-16-05-2022

The appeal was disposed of following an out-of-court settlement where the respondent agreed to install a video door phone and intercom facility within 30 days and provided interim access to an alternative club facility.

14
Stage 13Interim Order

Tribunal Order #0901126029342021-04-04-2022

The Tribunal noted that the parties have reached a settlement and directed both parties to complete the registry of the flat and execute the conveyance/lease deed in the interim.

15
Stage 14Interim Order

Tribunal Order #0901126029342021-31-03-2022

The Tribunal directed the appellant to appear in person and ordered the respondent's General Manager, Sri Satish Chandra Verma, to appear personally on the next date to facilitate a settlement regarding disputed dues and flat possession.

16
Stage 15Interim Order

Tribunal Order #0901126029342021-29-11-2021

The Tribunal allowed the limitation application, condoning a 54-day delay in filing the appeal based on Supreme Court precedents, and directed the registry to convert the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal was disposed of following an out-of-court settlement where the respondent agreed to install a video door phone and intercom facility within 30 days and provided interim access to an alternative club facility. Awarded in favor of Partial.

Disposal Winner: PartialStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal was disposed of following an out-of-court settlement where the respondent agreed to install a video door phone and intercom facility within 30 days and provided interim access to an alternative club facility.

Ruling Awarded To

Partial

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shailender Singh

Respondent Advocate(s)

  • Rajiv Shukla
  • Suyash Bajpai

Official RERA Tribunal Orders (5)

INTERIM_ORDEROrder ID: 0901126029342021-29-09-2021

The Tribunal issued a warning to the respondent's counsel for failing to file a vakalatnama and objections as promised, granting a final 10-day extension for filing objections to the condonation of delay application and grounds of appeal.

FINAL_ORDEROrder ID: 0901126029342021-16-05-2022

The appeal was disposed of following an out-of-court settlement where the respondent agreed to install a video door phone and intercom facility within 30 days and provided interim access to an alternative club facility.

INTERIM_ORDEROrder ID: 0901126029342021-04-04-2022

The Tribunal noted that the parties have reached a settlement and directed both parties to complete the registry of the flat and execute the conveyance/lease deed in the interim.

INTERIM_ORDEROrder ID: 0901126029342021-31-03-2022

The Tribunal directed the appellant to appear in person and ordered the respondent's General Manager, Sri Satish Chandra Verma, to appear personally on the next date to facilitate a settlement regarding disputed dues and flat possession.

INTERIM_ORDEROrder ID: 0901126029342021-29-11-2021

The Tribunal allowed the limitation application, condoning a 54-day delay in filing the appeal based on Supreme Court precedents, and directed the registry to convert the defective appeal into a regular appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paarth infrabuild pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →