Legal Issues & Claims Raised

Delay in Possession

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126029622023 by Aastha Infracity Limited against Rahul Kerkar before up_rera.

Delay in Possession
2
Stage 119/11/2024

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed Appeal-569/2023, finding the 150-day delay to be willful and without sufficient cause.

3
Stage 217/10/2024

Delay condonation

The Tribunal granted a request to adjourn the appeal for orders to 19.11.2024 and directed the parties to exchange pleadings in the interim.

4
Stage 318/09/2024

Delay condonation

The Tribunal granted an adjournment following a request from the respondent's counsel to review newly uploaded documents, scheduling the matter for 17.10.2024.

5
Stage 412/09/2024

Delay condonation

The Tribunal granted the appellant three days to upload required documents and scheduled the matter for orders/hearing on 18.09.2024.

6
Stage 502/09/2024

Delay condonation

The Tribunal granted the appellant five days to file a better affidavit for condonation of delay and directed the respondent to file a reply within three days thereafter. The matter is listed for hearing on 12.09.2024.

7
Stage 621/08/2024

Delay condonation

The Tribunal adjourned the proceedings due to an adjournment application filed by the appellant's counsel and rescheduled the hearing for September 2, 2024.

8
Stage 713/08/2024

Delay condonation

The Tribunal heard arguments regarding an application for condonation of delay and adjourned the appeal to 21.08.2024 for further arguments, noting that no further adjournments will be granted.

9
Stage 815/07/2024

Delay condonation

No text available.

10
Stage 915/05/2024

Delay condonation

No text available.

11
Stage 1018/04/2024

Delay condonation

The Tribunal granted the respondent three days to upload objections to the better affidavit and allowed the applicant one week to file a reply, scheduling the hearing for May 15, 2024.

12
Stage 1113/03/2024

Delay condonation

The Tribunal granted the respondent one week to file objections to a better affidavit regarding the application for condonation of delay and scheduled the matter for hearing on 18.04.2024.

13
Stage 1219/02/2024

Delay condonation

The Tribunal granted the appellant's counsel one week to file a better affidavit for condonation of delay and a reply to the grounds of appeal, scheduling the next hearing for 13.03.2024.

14
Stage 1309/01/2024

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on 19.02.2024 regarding the application for condonation of delay.

15
Stage 1403/10/2023

Delay condonation

No text available.

16
Stage 1521/08/2023

Delay condonation

The Tribunal verified the appellant's deposit of Rs. 6,87,584/- for compliance with Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduling the next hearing for 03.10.2023.

17
Stage 16Final Ruling Order

Tribunal Order #0901126029622023-19-11-2024

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed Appeal-569/2023, finding the 150-day delay to be willful and without sufficient cause.

18
Stage 17Interim Order

Tribunal Order #0901126029622023-21-08-2023

The Tribunal verified the appellant's deposit of Rs. 6,87,584/- for compliance with Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduling the next hearing for 03.10.2023.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed Appeal-569/2023, finding the 150-day delay to be willful and without sufficient cause. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed Appeal-569/2023, finding the 150-day delay to be willful and without sufficient cause.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Siddharth Nandwani
  • Samrat Vaish

Respondent Advocate(s)

  • Surangama Sharma

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126029622023-19-11-2024

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed Appeal-569/2023, finding the 150-day delay to be willful and without sufficient cause.

INTERIM_ORDEROrder ID: 0901126029622023-21-08-2023

The Tribunal verified the appellant's deposit of Rs. 6,87,584/- for compliance with Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduling the next hearing for 03.10.2023.