Appellant / Complainant
Rahul Sharma
Respondent
Aastha Infracity Limited
aastha infracity limited
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126052462023 by Rahul Sharma against Aastha Infracity Limited before up_rera.
Further Hearing
The Tribunal set aside the Regulatory Authority's order for a refund and restored the original complaint to address the legality of the unit's cancellation. The appellant is directed to file an amendment application challenging the cancellation, and the Regulatory Authority must frame a specific issue regarding its validity.
Hearing
The Tribunal granted time to the appellant's counsel to upload missing documents and adjourned the appeal for further hearing on 04.02.2025.
Delay condonation
The Tribunal allowed the application for condonation of delay, condoned any delay in instituting the appeal, and directed the Registry to convert the defective appeal into a regular appeal.
Delay condonation
The Tribunal granted a request by the appellant's counsel to list the appeal for orders/hearing on 18.12.2024 and directed the appellant to file a rejoinder affidavit in the interim.
Delay condonation
The Tribunal adjourned the appeal to 19.11.2024 at the request of the respondent's counsel and directed the parties to exchange pleadings in the interim.
Delay condonation
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the case for orders on 17.10.2024.
Delay condonation
The Tribunal closed the Respondent's opportunity to file objections to the grounds of appeal due to failure to comply with previous directions and granted the Appellant's request for adjournment denial. The matter is scheduled for final hearing on 06.09.2024, with a strict directive that no further extensions will be granted.
Delay condonation
The Tribunal granted the respondent one week to file objections to the grounds of appeal and provide a soft copy to the applicant, with the matter scheduled for hearing on 05.08.2024.
Delay condonation
The Tribunal directed the respondent to file objections to the grounds of appeal within one week and scheduled the matter for hearing on 03.07.2024.
Delay condonation
The Tribunal granted the respondent a final 10-day extension to file objections regarding the application for condonation of delay and the grounds of appeal, scheduling the next hearing for May 3, 2024.
Delay condonation
The Tribunal has revised the list and scheduled a hearing for 02.04.2024 to consider the condonation of delay in this defective appeal.
Delay condonation
The Tribunal ruled that service of notice to the respondent is sufficient based on delivery to various offices and via email, and granted the respondent ten days to file an objection.
Delay condonation
The Tribunal issued notice to the respondent regarding an appeal with a 102-day delay and directed the parties to exchange objections and replies via email and the e-portal before the next hearing on 18.01.2024.
Tribunal Order #0901126052462023-04-02-2025
The Tribunal set aside the Regulatory Authority's order for a refund and restored the original complaint to address the legality of the unit's cancellation. The appellant is directed to file an amendment application challenging the cancellation, and the Regulatory Authority must frame a specific issue regarding its validity.
Tribunal Order #0901126052462023-05-08-2024
The Tribunal closed the Respondent's opportunity to file objections to the grounds of appeal due to failure to comply with previous directions and granted the Appellant's request for adjournment denial. The matter is scheduled for final hearing on 06.09.2024, with a strict directive that no further extensions will be granted.
Tribunal Order #0901126052462023-18-12-2024
The Tribunal allowed the application for condonation of delay, condoned any delay in instituting the appeal, and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the Regulatory Authority's order for a refund and restored the original complaint to address the legality of the unit's cancellation. The appellant is directed to file an amendment application challenging the cancellation, and the Regulatory Authority must frame a specific issue regarding its validity. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the Regulatory Authority's order for a refund and restored the original complaint to address the legality of the unit's cancellation. The appellant is directed to file an amendment application challenging the cancellation, and the Regulatory Authority must frame a specific issue regarding its validity.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Surangama Sharma
Respondent Advocate(s)
- Siddharth Nandwani
- Samrat Vaish
Official RERA Tribunal Orders (3)
The Tribunal set aside the Regulatory Authority's order for a refund and restored the original complaint to address the legality of the unit's cancellation. The appellant is directed to file an amendment application challenging the cancellation, and the Regulatory Authority must frame a specific issue regarding its validity.
The Tribunal closed the Respondent's opportunity to file objections to the grounds of appeal due to failure to comply with previous directions and granted the Appellant's request for adjournment denial. The matter is scheduled for final hearing on 06.09.2024, with a strict directive that no further extensions will be granted.
The Tribunal allowed the application for condonation of delay, condoned any delay in instituting the appeal, and directed the Registry to convert the defective appeal into a regular appeal.