up_reraStatus: Completed
CASE ID: 0901126040432024

Appellant / Complainant

Rishabh Varshney

VS

Respondent

U.P. Awas Evam Vikas Parishad, The Uttar Pradesh Real Estate Regulatory Authority

Developer Firm

u.p. awas evam vikas parishad

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126040432024 by Rishabh Varshney against U.P. Awas Evam Vikas Parishad, The Uttar Pradesh Real Estate Regulatory Authority before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 129/08/2025

for delivery of Judgment/Order

The Tribunal ruled that the Limitation Act does not apply to complaints filed under the RERA Act 2016 and held that promoters cannot evade their statutory obligation to pay delay interest by citing laches or the execution of a conveyance deed. Consequently, the Tribunal quashed the Regulatory Authority's orders rejecting complaints on limitation grounds and restored the appeals for decision on merits.

3
Stage 223/04/2025

Further Hearing

The court has heard the arguments from the respective counsels and has reserved the judgment for further consideration.

4
Stage 321/04/2025

Further Hearing

No text available.

5
Stage 411/04/2025

Further Hearing

The Tribunal has adjourned the matter and scheduled the appeal for further hearing on April 21, 2025, at 1:30 p.m.

6
Stage 509/04/2025

Further Hearing

The Tribunal has adjourned the appeal to 11.04.2025 for hearing following a joint request from the counsel for both parties.

7
Stage 608/04/2025

For Order

The Tribunal refers the matter to a previous order passed in Appeal No. D 220/2024 (Jitendra Kumar Shukla Vs. U.P. Avas Evam Vikas Parishad) for the relevant directions.

8
Stage 728/03/2025

For Order

The Tribunal ordered that this appeal be listed before a Special Bench on 08.04.2025 along with other appeals of a similar nature.

9
Stage 825/02/2025

For Order

The Tribunal adjourned the appeal to 28.03.2025, noting that counsels are abstaining from judicial work due to a U.P. Bar Council resolution.

10
Stage 905/02/2025

For Order

The Tribunal granted a request for adjournment from the appellant's counsel and rescheduled the hearing for February 25, 2025.

11
Stage 1008/01/2025

For Order

The Tribunal adjourned the appeal to 05.02.2025 and directed the parties to exchange pleadings in the interim.

12
Stage 1110/12/2024

For Order

The Tribunal granted Respondent No. 2 ten days to file objections to the grounds of appeal and directed the appellant to file a reply within one week thereafter, scheduling the next hearing for January 8, 2025.

13
Stage 1208/11/2024

Admission

The Tribunal has admitted the appeal, issued notice to the respondent, and set a returnable date of December 10, 2024, while outlining the procedural requirements for service of notice and filing of objections.

14
Stage 13Final Ruling Order

Tribunal Order #0901126040432024-29-08-2025

The Tribunal ruled that the Limitation Act does not apply to complaints filed under the RERA Act 2016 and held that promoters cannot evade their statutory obligation to pay delay interest by citing laches or the execution of a conveyance deed. Consequently, the Tribunal quashed the Regulatory Authority's orders rejecting complaints on limitation grounds and restored the appeals for decision on merits.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal ruled that the Limitation Act does not apply to complaints filed under the RERA Act 2016 and held that promoters cannot evade their statutory obligation to pay delay interest by citing laches or the execution of a conveyance deed. Consequently, the Tribunal quashed the Regulatory Authority's orders rejecting complaints on limitation grounds and restored the appeals for decision on merits. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal ruled that the Limitation Act does not apply to complaints filed under the RERA Act 2016 and held that promoters cannot evade their statutory obligation to pay delay interest by citing laches or the execution of a conveyance deed. Consequently, the Tribunal quashed the Regulatory Authority's orders rejecting complaints on limitation grounds and restored the appeals for decision on merits.

Ruling Awarded To

Appellant

Interest Period

from the date of allotment/agreement till the date of offer of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav

Respondent Advocate(s)

  • Shireesh Kumar

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126040432024-29-08-2025

The Tribunal ruled that the Limitation Act does not apply to complaints filed under the RERA Act 2016 and held that promoters cannot evade their statutory obligation to pay delay interest by citing laches or the execution of a conveyance deed. Consequently, the Tribunal quashed the Regulatory Authority's orders rejecting complaints on limitation grounds and restored the appeals for decision on merits.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. awas evam vikas parishad?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →