up_reraStatus: Completed
CASE ID: 0901126053422022

Appellant / Complainant

U.P. Awas Evam Vikas Parishad

VS

Respondent

Deepak Goyal

Developer Firm

u.p. awas evam vikas parishad

Disputed Amount

37,76,902

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126053422022 by U.P. Awas Evam Vikas Parishad against Deepak Goyal before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 116/08/2023

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's order to refund the respondent's deposit with interest at MCLR+1% due to project abandonment and unfair contractual terms. The Tribunal further directed that the pre-deposited amount be transferred to the U.P. RERA for disbursement to the allottee during execution proceedings.

3
Stage 211/08/2023

Hearing

No text available.

4
Stage 307/07/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel to prepare their brief and rescheduled the hearing for August 11, 2023.

5
Stage 403/07/2023

Hearing

The Tribunal granted a request from the appellant's counsel for additional time to prepare the brief and rescheduled the appeal hearing for July 7, 2023.

6
Stage 519/05/2023

Delay condonation

The Tribunal condoned a 5-day delay in filing the appeal subject to a cost of Rs. 500 and directed the appellant to submit documentation regarding the decision to abandon the project in question.

7
Stage 607/04/2023

Delay condonation

No text available.

8
Stage 724/02/2023

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and directed the matter to be listed on 07.04.2023 for consideration of the delay condonation application.

9
Stage 824/01/2023

Delay condonation

No text available.

10
Stage 915/12/2022

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objection and scheduled the matter for hearing on January 24, 2023.

11
Stage 1021/11/2022

Delay condonation

No text available.

12
Stage 1114/10/2022

Delay condonation

No text available.

13
Stage 1214/09/2022

Delay condonation

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and set a returnable date of 14.10.2022.

14
Stage 13Final Ruling Order

Tribunal Order #0901126053422022-16-08-2023

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's order to refund the respondent's deposit with interest at MCLR+1% due to project abandonment and unfair contractual terms. The Tribunal further directed that the pre-deposited amount be transferred to the U.P. RERA for disbursement to the allottee during execution proceedings.

15
Stage 14Interim Order

Tribunal Order #0901126053422022-19-05-2023

The Tribunal condoned a 5-day delay in filing the appeal subject to a cost of Rs. 500 and directed the appellant to submit documentation regarding the decision to abandon the project in question.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's order to refund the respondent's deposit with interest at MCLR+1% due to project abandonment and unfair contractual terms. The Tribunal further directed that the pre-deposited amount be transferred to the U.P. RERA for disbursement to the allottee during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% p.a..

Disposal Winner: RespondentInterest Rate: MCLR+1% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's order to refund the respondent's deposit with interest at MCLR+1% due to project abandonment and unfair contractual terms. The Tribunal further directed that the pre-deposited amount be transferred to the U.P. RERA for disbursement to the allottee during execution proceedings.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1% p.a.

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • N N Pandey

Respondent Advocate(s)

  • Arjun Krishna

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126053422022-16-08-2023

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Regulatory Authority's order to refund the respondent's deposit with interest at MCLR+1% due to project abandonment and unfair contractual terms. The Tribunal further directed that the pre-deposited amount be transferred to the U.P. RERA for disbursement to the allottee during execution proceedings.

INTERIM_ORDEROrder ID: 0901126053422022-19-05-2023

The Tribunal condoned a 5-day delay in filing the appeal subject to a cost of Rs. 500 and directed the appellant to submit documentation regarding the decision to abandon the project in question.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. awas evam vikas parishad?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.