up_reraStatus: Completed
CASE ID: 0901126044222023

Appellant / Complainant

Ratnakar Gedam

VS

Respondent

Devika Gold Homz Pvt. Ltd.

Developer Firm

devika gold homz pvt. ltd.

Disputed Amount

15,32,706

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & ForfeitureMaintenance & Utility DisputesNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

29 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126044222023 by Ratnakar Gedam against Devika Gold Homz Pvt. Ltd. before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & ForfeitureMaintenance & Utility DisputesNon-Compliance & Execution
2
Stage 117/10/2025

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal allowed the appeals, setting aside the cancellation of three allotted units and the Regulatory Authority's order, while directing the respondent promoter to refund the deposited amounts with interest (MCLR+1%) and litigation costs.

3
Stage 230/07/2025

Hearing

The Tribunal noted the High Court's conditional stay on a previously imposed cost of Rs. 50,000/- and proceeded to hear arguments on the merits of the appeal, subsequently reserving judgment.

4
Stage 314/07/2025

Hearing

The Tribunal has granted a request by the respondent's counsel to list the appeal for orders or hearing on 30.07.2025.

5
Stage 422/05/2025

Hearing

The Tribunal rejected the respondent's application to recall a previous order imposing a cost of Rs. 50,000, noting that repeated adjournments were being used to harass the appellant. The respondent agreed to pay the cost within 10 days, failing which the appeal will proceed ex parte.

6
Stage 507/05/2025

Hearing

No text available.

7
Stage 615/04/2025

Hearing

The Tribunal granted the respondent additional time to file a rejoinder to the appellant's objections regarding a recall application and scheduled the matter for hearing on 07.05.2025.

8
Stage 708/04/2025

Hearing

The Tribunal has scheduled the appeal for hearing on 15.04.2025 to consider a recall application filed by the respondent and directed the appellant to file objections to said application.

9
Stage 817/03/2025

Hearing

The Tribunal imposed a cost of Rs. 50,000 on the respondent for non-cooperation and repeated requests for adjournment, warning that the case will proceed ex parte if they fail to appear at the next hearing.

10
Stage 912/02/2025

Hearing

The Tribunal has scheduled the case for orders or final hearing on March 17, 2025.

11
Stage 1024/01/2025

Hearing

Upon the joint request of the counsels for both parties, the Tribunal has adjourned the hearing of the appeal to 12.02.2025.

12
Stage 1119/12/2024

Hearing

The Tribunal granted a request from the respondent's counsel to list the appeal for hearing on 24.01.2025, noting that no further adjournments will be permitted.

13
Stage 1222/11/2024

Hearing

The Tribunal has adjourned the appeal to 19.12.2024 following a request from the respondent's counsel.

14
Stage 1317/10/2024

Hearing

The Tribunal granted an adjournment requested by the respondent but imposed a cost of Rs. 10,000/- to be paid by the respondent to the appellant.

15
Stage 1420/09/2024

Admission

The Tribunal granted a final opportunity to the respondent to argue the matter on the next date and scheduled the appeal for a final hearing on 17.10.2024, stipulating that no further adjournments will be permitted.

16
Stage 1520/08/2024

Admission

The Tribunal noted that the appellant has filed a rejoinder to the respondent's objections and, upon joint request from both parties, adjourned the matter for final hearing on 20.09.2024.

17
Stage 1619/07/2024

Admission

The Tribunal granted the appellant three days to file a rejoinder to the respondent's objections and scheduled the next hearing for August 20, 2024.

18
Stage 1719/04/2024

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the next hearing for May 20, 2024.

19
Stage 1814/03/2024

Delay condonation

The Tribunal deprecated the respondent's counsel's conduct regarding an adjournment request and granted a final one-week extension for the respondent to file objections and vakalatnama.

20
Stage 1908/02/2024

Admission

The Tribunal granted the respondent 10 days to file objections and directed them to provide a soft copy of said objections to the applicant's counsel, with the matter listed for hearing on 14.03.2024.

21
Stage 2009/11/2023

Admission

No text available.

22
Stage 2126/09/2023

Admission

The Tribunal issued notice to the respondent and outlined the procedural requirements for service of notice and the exchange of objections and replies before the next hearing on 09.11.2023.

23
Stage 22Interim Order

Tribunal Order #0901126044222023-30-07-2025

The Tribunal noted the High Court's conditional stay on a previously imposed cost of Rs. 50,000/- and proceeded to hear arguments on the merits of the appeal, subsequently reserving judgment.

24
Stage 23Interim Order

Tribunal Order #0901126044222023-17-10-2024

The Tribunal granted an adjournment requested by the respondent but imposed a cost of Rs. 10,000/- to be paid by the respondent to the appellant.

25
Stage 24Final Ruling Order

Tribunal Order #0901126044222023-17-10-2025

The U.P. Real Estate Appellate Tribunal allowed the appeals, setting aside the cancellation of three allotted units and the Regulatory Authority's order, while directing the respondent promoter to refund the deposited amounts with interest (MCLR+1%) and litigation costs.

26
Stage 25Interim Order

Tribunal Order #0901126044222023-22-05-2025

The Tribunal rejected the respondent's application to recall a previous order imposing a cost of Rs. 50,000, noting that repeated adjournments were being used to harass the appellant. The respondent agreed to pay the cost within 10 days, failing which the appeal will proceed ex parte.

27
Stage 26Interim Order

Tribunal Order #0901126044222023-17-03-2025

The Tribunal imposed a cost of Rs. 50,000 on the respondent for non-cooperation and repeated requests for adjournment, warning that the case will proceed ex parte if they fail to appear at the next hearing.

28
Stage 27Interim Order

Tribunal Order #0901126044222023-14-03-2024

The Tribunal deprecated the respondent's counsel's conduct regarding an adjournment request and granted a final one-week extension for the respondent to file objections and vakalatnama.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal allowed the appeals, setting aside the cancellation of three allotted units and the Regulatory Authority's order, while directing the respondent promoter to refund the deposited amounts with interest (MCLR+1%) and litigation costs. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal allowed the appeals, setting aside the cancellation of three allotted units and the Regulatory Authority's order, while directing the respondent promoter to refund the deposited amounts with interest (MCLR+1%) and litigation costs.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

from the date of deposit till the date of actual payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)Section 11(4)(d)Section 19(6)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • A
  • Samrat Vaish

Respondent Advocate(s)

  • Siddharth Nandwani
  • Abhishek Khare
  • Aahuti Agarwal
  • Pranjal Mishra

Official RERA Tribunal Orders (6)

INTERIM_ORDEROrder ID: 0901126044222023-30-07-2025

The Tribunal noted the High Court's conditional stay on a previously imposed cost of Rs. 50,000/- and proceeded to hear arguments on the merits of the appeal, subsequently reserving judgment.

INTERIM_ORDEROrder ID: 0901126044222023-17-10-2024

The Tribunal granted an adjournment requested by the respondent but imposed a cost of Rs. 10,000/- to be paid by the respondent to the appellant.

FINAL_ORDEROrder ID: 0901126044222023-17-10-2025

The U.P. Real Estate Appellate Tribunal allowed the appeals, setting aside the cancellation of three allotted units and the Regulatory Authority's order, while directing the respondent promoter to refund the deposited amounts with interest (MCLR+1%) and litigation costs.

INTERIM_ORDEROrder ID: 0901126044222023-22-05-2025

The Tribunal rejected the respondent's application to recall a previous order imposing a cost of Rs. 50,000, noting that repeated adjournments were being used to harass the appellant. The respondent agreed to pay the cost within 10 days, failing which the appeal will proceed ex parte.

INTERIM_ORDEROrder ID: 0901126044222023-17-03-2025

The Tribunal imposed a cost of Rs. 50,000 on the respondent for non-cooperation and repeated requests for adjournment, warning that the case will proceed ex parte if they fail to appear at the next hearing.

INTERIM_ORDEROrder ID: 0901126044222023-14-03-2024

The Tribunal deprecated the respondent's counsel's conduct regarding an adjournment request and granted a final one-week extension for the respondent to file objections and vakalatnama.

TathyaGrid RERA Intelligence AI

Need to research all rulings for devika gold homz pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →