up_reraStatus: Completed
CASE ID: 0901126044712021

Appellant / Complainant

Ramchandra Prasad Singh

VS

Respondent

Devika Gold Homz Pvt. Ltd.

Developer Firm

devika gold homz pvt. ltd.

Disputed Amount

53,05,378

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

48 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126044712021 by Ramchandra Prasad Singh against Devika Gold Homz Pvt. Ltd. before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 104/09/2025

for delivery of Judgment/Order

The Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposit for five units with interest at MCLR+1% due to project delays, while also awarding litigation costs of Rs. 25,000.

3
Stage 205/08/2025

Further Hearing

The Tribunal heard arguments from the counsel for both the appellant and the respondent, and subsequently reserved the judgment for further delivery.

4
Stage 331/07/2025

Further Hearing

The Tribunal has adjourned the appeal to 05.08.2025 for orders or hearing upon the request of the respondent's counsel.

5
Stage 415/07/2025

Further Hearing

No text available.

6
Stage 522/05/2025

Further Hearing

The Tribunal heard arguments regarding the allottee's right to withdraw from a project following a claim of deemed OC/CC and scheduled the appeal for further hearing on 15.07.2025.

7
Stage 607/05/2025

Further Hearing

No text available.

8
Stage 730/04/2025

Hearing

The Tribunal adjourned the matter for further hearing on 07.05.2025 following a request from the respondent's counsel, as previous arguments were inconclusive.

9
Stage 808/04/2025

Hearing

The Tribunal has scheduled the defective appeal for consideration of the application for condonation of delay and a subsequent hearing on April 30, 2025, following a joint request from the parties' counsel.

10
Stage 917/03/2025

Hearing

The Tribunal granted an adjournment request from the respondent's counsel and rescheduled the appeal for hearing on 08.04.2025, noting that no further adjournments will be permitted.

11
Stage 1012/02/2025

Hearing

The Tribunal has scheduled the case for orders or final hearing on March 17, 2025.

12
Stage 1124/01/2025

Hearing

The Tribunal has granted a request to list the case for orders on 12.02.2025.

13
Stage 1219/12/2024

Hearing

The Tribunal has rescheduled the hearing of Appeal-756/2021 to 24.01.2025 upon the request of the respondent's counsel, noting that no further adjournments will be permitted.

14
Stage 1322/11/2024

Hearing

The Tribunal has granted a request by the respondent's counsel to reschedule the hearing of the appeal to 19.12.2024.

15
Stage 1418/10/2024

Hearing

The Tribunal adjourned the matter to 22.11.2024 and imposed a cost of Rs. 10,000/- on the respondent to be paid to the appellant due to delays caused by the respondent's repeated engagement of new counsel.

16
Stage 1513/09/2024

Hearing

The Tribunal directed the office to place the hard copies of the respondent's objections and the appellant's reply on record and scheduled the case for hearing on 18.10.2024.

17
Stage 1628/08/2024

Hearing

The Tribunal noted the submission of the respondent's objection and adjourned the matter to 13.09.2024 for final arguments.

18
Stage 1725/07/2024

Hearing

The Tribunal granted the respondent seven days to provide hard copies of their objections and scheduled the appeal for a final hearing on 28.08.2024.

19
Stage 1830/05/2024

Hearing

The Tribunal noted that the appeal is ready for hearing and scheduled the matter for a hearing on 25.07.2024.

20
Stage 1929/04/2024

Hearing

No text available.

21
Stage 2022/03/2024

Hearing

The tribunal granted an adjournment requested by the respondent's counsel due to family issues and rescheduled the hearing for 29.04.2024.

22
Stage 2121/02/2024

Hearing

The Tribunal granted the parties a one-week extension to file physical copies of their objections and replies and scheduled the matter for hearing on 22.03.2024.

23
Stage 2212/01/2024

Hearing

The Tribunal directed the parties to file physical copies of their pleadings due to the age of the case and scheduled the appeal for hearing on 21.02.2024.

24
Stage 2311/10/2023

Hearing

No text available.

25
Stage 2425/08/2023

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 11.10.2023.

26
Stage 2508/08/2023

Hearing

The Tribunal notes that pleadings have been exchanged and the appeal is ripe for hearing, subsequently listing the matter for hearing on 25.08.2023.

27
Stage 2626/05/2023

Hearing

No text available.

28
Stage 2725/04/2023

Hearing

This document appears to be a formal header and appearance record for Appeal-756/2021, noting the presence of counsel for both the appellant and the respondent before the U.P. Real Estate Appellate Tribunal.

29
Stage 2823/03/2023

Hearing

The Tribunal noted that pleadings have been exchanged and the case is ripe for hearing, subsequently listing the matter for orders/hearing on 25.04.2023.

30
Stage 2915/02/2023

Hearing

The Tribunal denied requests for adjournment from the appellant's counsel due to them being out of station and scheduled the appeal for a hearing on 23.03.2023.

31
Stage 3013/01/2023

Hearing

No text available.

32
Stage 3112/12/2022

Hearing

No text available.

33
Stage 3216/11/2022

Hearing

The tribunal adjourned the proceedings because no one appeared for the appellant and the respondent's counsel were on sanctioned leave. The matter is rescheduled for hearing on 12.12.2022.

34
Stage 3311/10/2022

Hearing

The appeal was adjourned/relisted upon the request of the appellant's counsel.

35
Stage 3413/09/2022

Hearing

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and directed the submission of the reply via email and the e-portal.

36
Stage 3522/08/2022

Further Order

The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and scheduled the appeal for a hearing on 13.09.2022.

37
Stage 3622/07/2022

Further Order

The Tribunal granted a final 10-day extension for the respondent to file their Vakalatnama and objections, warning that the matter will proceed ex-parte if they fail to comply by the next hearing on 22.08.2022.

38
Stage 3712/05/2022

Hearing

The Tribunal granted the respondent a final opportunity to file their Vakalatnama and directed them to file a reply to the memo of appeal within two weeks.

39
Stage 3806/04/2022

Hearing

The Tribunal directed the respondent's counsel to file a Vakalatnama and a reply to the grounds of appeal within one week and scheduled the case for hearing on 12.05.2022.

40
Stage 3916/03/2022

Further Order

The Tribunal granted an adjournment requested by the respondent's counsel due to a medical emergency and directed the parties to exchange pleadings in the interim.

41
Stage 4003/02/2022

Further Order

No text available.

42
Stage 4110/01/2022

Notice

The Tribunal noted that the appeal was filed within the limitation period and directed the respondent to file objections and serve them to the appellant's counsel via email by the next hearing date of 03.02.2022.

43
Stage 4210/12/2021

Notice

The Tribunal directed the respondent to file objections to the grounds of appeal within two weeks and scheduled the next hearing for January 10, 2022.

44
Stage 4318/11/2021

Hearing on Appeal

The Tribunal noted that all registry defects were removed and ordered that notice be issued to the respondent via registered post and e-mail, with the case listed for further orders on 10.12.2021.

45
Stage 44Final Ruling Order

Tribunal Order #0901126044712021-04-09-2025

The Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposit for five units with interest at MCLR+1% due to project delays, while also awarding litigation costs of Rs. 25,000.

46
Stage 45Interim Order

Tribunal Order #0901126044712021-18-10-2024

The Tribunal adjourned the matter to 22.11.2024 and imposed a cost of Rs. 10,000/- on the respondent to be paid to the appellant due to delays caused by the respondent's repeated engagement of new counsel.

47
Stage 46Interim Order

Tribunal Order #0901126044712021-22-07-2022

The Tribunal granted a final 10-day extension for the respondent to file their Vakalatnama and objections, warning that the matter will proceed ex-parte if they fail to comply by the next hearing on 22.08.2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposit for five units with interest at MCLR+1% due to project delays, while also awarding litigation costs of Rs. 25,000. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposit for five units with interest at MCLR+1% due to project delays, while also awarding litigation costs of Rs. 25,000.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Dhruvendra Pratap Singh

Respondent Advocate(s)

  • Abhishek Khare
  • Siddharth Nandwani
  • Aahuti Agarwal
  • N A
  • Pranjal Mishra

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126044712021-04-09-2025

The Tribunal set aside the Regulatory Authority's order and directed the respondent promoter to refund the appellant's deposit for five units with interest at MCLR+1% due to project delays, while also awarding litigation costs of Rs. 25,000.

INTERIM_ORDEROrder ID: 0901126044712021-18-10-2024

The Tribunal adjourned the matter to 22.11.2024 and imposed a cost of Rs. 10,000/- on the respondent to be paid to the appellant due to delays caused by the respondent's repeated engagement of new counsel.

INTERIM_ORDEROrder ID: 0901126044712021-22-07-2022

The Tribunal granted a final 10-day extension for the respondent to file their Vakalatnama and objections, warning that the matter will proceed ex-parte if they fail to comply by the next hearing on 22.08.2022.

TathyaGrid RERA Intelligence AI

Need to research all rulings for devika gold homz pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →