up_reraStatus: Completed
CASE ID: 0901126046852024

Appellant / Complainant

Samrat Basu

VS

Respondent

Dhanya Promoters Private Limited (Mahagun Group)

Developer Firm

dhanya promoters private limited

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

35 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126046852024 by Samrat Basu against Dhanya Promoters Private Limited (Mahagun Group) before up_rera.

Non-Compliance & Execution
2
Stage 111/05/2026

Execution

The Tribunal disposed of the execution application (EA-8/2024) as the decree holder submitted that the judgment amount has been fully satisfied.

3
Stage 210/04/2026

Execution

The Tribunal directed the Registry to remit Rs. 75,06,814/ recovered from the judgment debtor to the decree holder and scheduled a hearing for May 11, 2026, to determine if additional amounts are owed.

4
Stage 316/03/2026

Execution

The Tribunal issued a bailable warrant against the District Magistrate of Gautam Budh Nagar for failure to respond to notices regarding the execution of a judgment and decree.

5
Stage 410/03/2026

Execution

The Tribunal directed the Registry to furnish the status of the compliance report from the Collector of Gautam Budha Nagar and adjourned the matter to 16.03.2026.

6
Stage 505/02/2026

Execution

The Tribunal issued a show cause notice to the DM/Collector, Gautam Budh Nagar, for failing to comply with an attachment order regarding the judgment debtor's property and bank accounts.

7
Stage 612/01/2026

Execution

The Tribunal directed the Registry to issue a fresh reminder to the District Magistrate, Gautam Buddh Nagar, regarding the non-compliance of a previously sent attachment order.

8
Stage 701/12/2025

Execution

The Tribunal directed the Registry to issue a fresh reminder to the District Magistrate, Gautam Buddha Nagar, regarding the non-compliance of a previously sent attachment order.

9
Stage 806/11/2025

Execution

The Tribunal directed the Registry to issue a reminder to the District Magistrate of Gautam Buddha Nagar to ensure compliance with the previous order regarding the attachment of the judgment debtor's property and bank accounts.

10
Stage 913/10/2025

Execution

The Tribunal directed the Registry to report on the compliance of previous orders regarding the issuance of notices and instructed the re-sending of a letter to the District Magistrate, Gautam Budh Nagar, following an unserved communication.

11
Stage 1012/09/2025

Execution

The Tribunal issued fresh notices for the execution application and directed a show cause notice under Section 64 of the Act to determine why penal action should not be taken against the respondent judgment debtor.

12
Stage 1104/09/2025

Execution

The Tribunal directed the Registry to submit a report and scheduled the matter for orders or hearing on 12.09.2025.

13
Stage 1204/08/2025

Execution

The Tribunal directed the District Magistrate/Collector of Gautam Budh Nagar to attach the respondent's property and bank accounts, excluding the RERA escrow account, to the extent of Rs. 75,06,814/-.

14
Stage 1322/07/2025

Execution

The Tribunal directed the Registry to submit a compliance report regarding a previous order dated 30.05.2025 and to verify if HDFC Bank Ltd. has complied with said order.

15
Stage 1430/05/2025

Execution

The Tribunal directed the Branch Manager of HDFC Bank Limited, Vaishali Ghaziabad, to attach the respondent's bank accounts to the extent of Rs. 75,06,814 to satisfy the decreed amount.

16
Stage 1523/05/2025

Execution

The Tribunal noted the computation of the amount due to the appellant decree holder, amounting to Rs. 75,06,814/- as of 06.05.2025, and directed the appellant to provide the respondent's bank account details.

17
Stage 1608/05/2025

Execution

The court granted the decree holder additional time to upload the computation and scheduled the case for orders on May 23, 2025.

18
Stage 1715/04/2025

Execution

The Tribunal deemed the service of notice upon the respondent sufficient and directed the appellant to file a computation of the amount due pursuant to the judgment dated 21.10.2024.

19
Stage 1818/03/2025

Execution

The Tribunal adjourned the hearing of EA-8/2024 to 15.04.2025 because lawyers were abstaining from judicial work following a resolution by the Real Estate Bar Association, Lucknow.

20
Stage 1921/02/2025

Execution

The Tribunal directed the appellant to take fresh steps following the order dated 29.01.2025 and scheduled the matter for hearing on 18.03.2025.

21
Stage 2029/01/2025

Execution

The Tribunal issued notice to the respondent regarding the execution application and outlined the procedural timeline for service of notice and filing of objections.

22
Stage 2122/01/2025

Execution

No text available.

23
Stage 2215/01/2025

Execution

No text available.

24
Stage 23Interim Order

Tribunal Order #0901126046852024-10-04-2026

The Tribunal directed the Registry to remit Rs. 75,06,814/ recovered from the judgment debtor to the decree holder and scheduled a hearing for May 11, 2026, to determine if additional amounts are owed.

25
Stage 24Interim Order

Tribunal Order #0901126046852024-16-03-2026

The Tribunal issued a bailable warrant against the District Magistrate of Gautam Budh Nagar for failure to respond to notices regarding the execution of a judgment and decree.

26
Stage 25Interim Order

Tribunal Order #0901126046852024-12-01-2026

The Tribunal directed the Registry to issue a fresh reminder to the District Magistrate, Gautam Buddh Nagar, regarding the non-compliance of a previously sent attachment order.

27
Stage 26Interim Order

Tribunal Order #0901126046852024-30-05-2025

The Tribunal directed the Branch Manager of HDFC Bank Limited, Vaishali Ghaziabad, to attach the respondent's bank accounts to the extent of Rs. 75,06,814 to satisfy the decreed amount.

28
Stage 27Interim Order

Tribunal Order #0901126046852024-06-11-2025

The Tribunal directed the Registry to issue a reminder to the District Magistrate of Gautam Buddha Nagar to ensure compliance with the previous order regarding the attachment of the judgment debtor's property and bank accounts.

29
Stage 28Interim Order

Tribunal Order #0901126046852024-12-09-2025

The Tribunal issued fresh notices for the execution application and directed a show cause notice under Section 64 of the Act to determine why penal action should not be taken against the respondent judgment debtor.

30
Stage 29Interim Order

Tribunal Order #0901126046852024-04-08-2025

The Tribunal directed the District Magistrate/Collector of Gautam Budh Nagar to attach the respondent's property and bank accounts, excluding the RERA escrow account, to the extent of Rs. 75,06,814/-.

31
Stage 30Interim Order

Tribunal Order #0901126046852024-05-02-2026

The Tribunal issued a show cause notice to the DM/Collector, Gautam Budh Nagar, for failing to comply with an attachment order regarding the judgment debtor's property and bank accounts.

32
Stage 31Interim Order

Tribunal Order #0901126046852024-01-12-2025

The Tribunal directed the Registry to issue a fresh reminder to the District Magistrate, Gautam Buddha Nagar, regarding the non-compliance of a previously sent attachment order.

33
Stage 32Interim Order

Tribunal Order #0901126046852024-15-04-2025

The Tribunal deemed the service of notice upon the respondent sufficient and directed the appellant to file a computation of the amount due pursuant to the judgment dated 21.10.2024.

34
Stage 33Interim Order

Tribunal Order #0901126046852024-23-05-2025

The Tribunal noted the computation of the amount due to the appellant decree holder, amounting to Rs. 75,06,814/- as of 06.05.2025, and directed the appellant to provide the respondent's bank account details.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Disposed of Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Disposed of

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Mandeep Singh

Official RERA Tribunal Orders (11)

INTERIM_ORDEROrder ID: 0901126046852024-10-04-2026

The Tribunal directed the Registry to remit Rs. 75,06,814/ recovered from the judgment debtor to the decree holder and scheduled a hearing for May 11, 2026, to determine if additional amounts are owed.

INTERIM_ORDEROrder ID: 0901126046852024-16-03-2026

The Tribunal issued a bailable warrant against the District Magistrate of Gautam Budh Nagar for failure to respond to notices regarding the execution of a judgment and decree.

INTERIM_ORDEROrder ID: 0901126046852024-12-01-2026

The Tribunal directed the Registry to issue a fresh reminder to the District Magistrate, Gautam Buddh Nagar, regarding the non-compliance of a previously sent attachment order.

INTERIM_ORDEROrder ID: 0901126046852024-30-05-2025

The Tribunal directed the Branch Manager of HDFC Bank Limited, Vaishali Ghaziabad, to attach the respondent's bank accounts to the extent of Rs. 75,06,814 to satisfy the decreed amount.

INTERIM_ORDEROrder ID: 0901126046852024-06-11-2025

The Tribunal directed the Registry to issue a reminder to the District Magistrate of Gautam Buddha Nagar to ensure compliance with the previous order regarding the attachment of the judgment debtor's property and bank accounts.

INTERIM_ORDEROrder ID: 0901126046852024-12-09-2025

The Tribunal issued fresh notices for the execution application and directed a show cause notice under Section 64 of the Act to determine why penal action should not be taken against the respondent judgment debtor.

INTERIM_ORDEROrder ID: 0901126046852024-04-08-2025

The Tribunal directed the District Magistrate/Collector of Gautam Budh Nagar to attach the respondent's property and bank accounts, excluding the RERA escrow account, to the extent of Rs. 75,06,814/-.

INTERIM_ORDEROrder ID: 0901126046852024-05-02-2026

The Tribunal issued a show cause notice to the DM/Collector, Gautam Budh Nagar, for failing to comply with an attachment order regarding the judgment debtor's property and bank accounts.

INTERIM_ORDEROrder ID: 0901126046852024-01-12-2025

The Tribunal directed the Registry to issue a fresh reminder to the District Magistrate, Gautam Buddha Nagar, regarding the non-compliance of a previously sent attachment order.

INTERIM_ORDEROrder ID: 0901126046852024-15-04-2025

The Tribunal deemed the service of notice upon the respondent sufficient and directed the appellant to file a computation of the amount due pursuant to the judgment dated 21.10.2024.

INTERIM_ORDEROrder ID: 0901126046852024-23-05-2025

The Tribunal noted the computation of the amount due to the appellant decree holder, amounting to Rs. 75,06,814/- as of 06.05.2025, and directed the appellant to provide the respondent's bank account details.

TathyaGrid RERA Intelligence AI

Need to research all rulings for dhanya promoters private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →