up_reraStatus: Completed
CASE ID: 0901126059222021

Appellant / Complainant

Sharad Kumar

VS

Respondent

Radhey Krishna Techno Build Pvt Ltd

Developer Firm

radhey krishna techno build pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

36 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126059222021 by Sharad Kumar against Radhey Krishna Techno Build Pvt Ltd before up_rera.

2
Stage 117/12/2024

Hearing

The appellant filed an application to withdraw the appeal following an amicable settlement between the parties, and the Tribunal allowed the withdrawal, resulting in the dismissal of the appeal.

3
Stage 229/11/2024

Hearing

No text available.

4
Stage 323/10/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the hearing for November 29, 2024.

5
Stage 419/09/2024

Hearing

The Tribunal granted the appellant seven days to file objections against a calculation chart submitted by the respondent and scheduled the matter for orders on 23.10.2024.

6
Stage 516/08/2024

Hearing

No text available.

7
Stage 623/07/2024

Hearing

The Tribunal directed the respondent to upload a calculation chart of outstanding dues and ordered the appellant to file objections within 7 days, scheduling the next hearing for 16.08.2024.

8
Stage 711/07/2024

Hearing

The Tribunal granted the respondent a final one-week extension to inform the appellant of the outstanding amount owed under the Regulatory Authority's order, with the next hearing scheduled for 23.07.2024.

9
Stage 814/05/2024

Hearing

The Tribunal directed the respondent to comply with a previous order dated 02.05.2024 regarding the disclosure of outstanding amounts, warning that the CMD will be summoned for non-compliance.

10
Stage 902/05/2024

Hearing

The Tribunal granted the respondent counsel time to seek instructions and provide the exact outstanding amount due, subsequently adjourning the appeal to 14.05.2024.

11
Stage 1003/04/2024

Hearing

The Tribunal adjourned the matter to 02.05.2024 and issued a strict directive that no further adjournments will be granted, warning that the case will be decided based on available records if parties fail to appear.

12
Stage 1101/03/2024

Hearing

The Tribunal noted the absence of both the appellant and the respondent's counsel due to illness and adjourned the matter for hearing on 03.04.2024.

13
Stage 1225/01/2024

Hearing

The Tribunal noted the absence of both counsels due to illness and sanctioned leave, subsequently adjourning the matter to 01.03.2024.

14
Stage 1327/10/2023

Hearing

No text available.

15
Stage 1415/09/2023

Hearing

Upon the joint request of the counsels for both parties, the appeal has been scheduled for a hearing on 27.10.2023.

16
Stage 1518/08/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to his engagement at the High Court and rescheduled the hearing for 15.09.2023.

17
Stage 1610/08/2023

Hearing

Upon the joint request of the counsel for both parties, the Tribunal has adjourned the appeal and scheduled it to be listed on 18.08.2023.

18
Stage 1730/05/2023

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 10.08.2023.

19
Stage 1819/04/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the case for hearing on 30.05.2023.

20
Stage 1903/03/2023

Exchange of pleadings

The Tribunal noted that pleadings have been exchanged and the case is ripe for hearing, subsequently listing the matter for orders/hearing on 19.04.2023.

21
Stage 2001/02/2023

Exchange of pleadings

No text available.

22
Stage 2116/12/2022

Exchange of pleadings

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the appeal for hearing on 01.02.2023.

23
Stage 2221/11/2022

Exchange of pleadings

No text available.

24
Stage 2331/10/2022

Exchange of pleadings

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 21.11.2022.

25
Stage 2421/09/2022

Exchange of pleadings

The Tribunal granted the appellant's request for a short date to file a replication/rejoinder against the respondent's reply and scheduled the next hearing for 31.10.2022.

26
Stage 2524/08/2022

Exchange of pleadings

The Tribunal directed the respondent's counsel to file a Vakalatnama within two days and ordered the appellant to file a replication/rejoinder before the next hearing on 21.09.2022.

27
Stage 2612/07/2022

Further Order

The Tribunal directed the appellant to file a replication/rejoinder to the respondent's reply and scheduled the next hearing for August 24, 2022.

28
Stage 2702/05/2022

Further Order

The Tribunal granted the respondent time to file a reply to the grounds of appeal and directed the appellant to submit a replication within one week after receiving said reply, scheduling the next hearing for 12.07.2022.

29
Stage 2824/03/2022

Hearing

The Tribunal condoned a 26-day delay in filing the appeal due to the COVID-19 pandemic period and directed the respondent to file a reply to the grounds of appeal.

30
Stage 2925/02/2022

Delay condonation

The Tribunal directed the respondent to file objections to the condonation of delay application and grounds of appeal within 10 days, scheduling the next hearing for March 24, 2022.

31
Stage 3017/01/2022

Delay condonation

No text available.

32
Stage 3115/12/2021

Delay condonation

The Tribunal noted that the appeal was filed beyond the limitation period and directed that notice be issued to the respondent via registered post and email.

33
Stage 32Interim Order

Tribunal Order #0901126059222021-03-04-2024

The Tribunal adjourned the matter to 02.05.2024 and issued a strict directive that no further adjournments will be granted, warning that the case will be decided based on available records if parties fail to appear.

34
Stage 33Interim Order

Tribunal Order #0901126059222021-24-03-2022

The Tribunal condoned a 26-day delay in filing the appeal due to the COVID-19 pandemic period and directed the respondent to file a reply to the grounds of appeal.

35
Stage 34Interim Order

Tribunal Order #0901126059222021-14-05-2024

The Tribunal directed the respondent to comply with a previous order dated 02.05.2024 regarding the disclosure of outstanding amounts, warning that the CMD will be summoned for non-compliance.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • N A

Respondent Advocate(s)

  • Anurag Singh

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126059222021-03-04-2024

The Tribunal adjourned the matter to 02.05.2024 and issued a strict directive that no further adjournments will be granted, warning that the case will be decided based on available records if parties fail to appear.

INTERIM_ORDEROrder ID: 0901126059222021-24-03-2022

The Tribunal condoned a 26-day delay in filing the appeal due to the COVID-19 pandemic period and directed the respondent to file a reply to the grounds of appeal.

INTERIM_ORDEROrder ID: 0901126059222021-14-05-2024

The Tribunal directed the respondent to comply with a previous order dated 02.05.2024 regarding the disclosure of outstanding amounts, warning that the CMD will be summoned for non-compliance.

TathyaGrid RERA Intelligence AI

Need to research all rulings for radhey krishna techno build pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →