up_reraStatus: Completed
CASE ID: 0901126002252019

Appellant / Complainant

Nishi Kant Rai

VS

Respondent

Paramount Probuild Pvt. Ltd.

Developer Firm

paramount probuild pvt. ltd.

Disputed Amount

4,51,956

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

54 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002252019 by Nishi Kant Rai against Paramount Probuild Pvt. Ltd. before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes
2
Stage 102/12/2025

Part Heard

The Tribunal allowed the appeals, directing the respondent promoter to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal additional charges and enhanced super area payments with interest, and commence maintenance charges only from the date of physical possession.

3
Stage 227/11/2025

Hearing

The Tribunal has granted a request to list the appeal as a part-heard matter on 02.12.2025.

4
Stage 313/11/2025

Further Hearing

The Tribunal granted a mutual request for adjournment from both parties and rescheduled the case for orders on 27.11.2025, noting that no further adjournments will be permitted.

5
Stage 403/11/2025

Further Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for hearing on 13.11.2025, noting that no further adjournments will be permitted.

6
Stage 509/10/2025

Further Hearing

The Tribunal heard arguments from both parties but found them inconclusive and adjourned the appeal for further hearing on 03.11.2025.

7
Stage 609/09/2025

Further Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 09.10.2025.

8
Stage 727/08/2025

Further Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the case for orders on 09.09.2025, noting that no further adjournments will be permitted.

9
Stage 812/08/2025

Further Hearing

The Tribunal granted the respondent time to upload documents regarding disputed charges and adjourned the matter to 27.08.2025 for orders or further hearing.

10
Stage 930/07/2025

Further Hearing

The Tribunal directed the respondent/promoter to ensure the appellant or their tenant has unhindered ingress and egress to the unit, including the right to move goods and furniture in or out.

11
Stage 1014/07/2025

Further Hearing

The Tribunal granted the respondent a one-week extension to comply with a previous order and directed the respondent promoter to provide all admissible maintenance services to the appellant, who is currently paying maintenance charges from the date of possession.

12
Stage 1121/05/2025

Further Hearing

The respondent's counsel requested and was granted additional time to comply with the previous order dated 07.03.2025, with the case scheduled for orders on 14.07.2025.

13
Stage 1230/04/2025

Further Hearing

The Tribunal granted a request from the respondent's counsel to adjourn the matter and scheduled the next hearing for 21.05.2025, allowing parties to exchange pleadings in the interim.

14
Stage 1303/04/2025

Further Hearing

The Tribunal granted the appellant's counsel additional time to comply with a previous order and rescheduled the case for hearing on 30.04.2025.

15
Stage 1407/03/2025

Further Hearing

The Tribunal directed the respondent to file an affidavit explaining the execution of additional FAR and ordered the appellant to deposit maintenance fees from the date of possession, pending the appeal outcome.

16
Stage 1512/02/2025

Hearing

At the request of the respondent's counsel, the tribunal has adjourned the appeal and scheduled it for a hearing on March 7, 2025.

17
Stage 1624/01/2025

Hearing

The Tribunal has scheduled the case for orders on February 12, 2025, noting the absence of the respondent's counsel.

18
Stage 1720/12/2024

Hearing

The Tribunal directed the respondent/promoter to submit the super area computation and provide a categorical statement regarding compliance with building bye-laws, while scheduling the next hearing for January 24, 2025.

19
Stage 1820/11/2024

Hearing

The court adjourned the proceedings at the request of the respondent's counsel and rescheduled the hearing for December 20, 2024, noting that no further adjournments will be granted.

20
Stage 1915/10/2024

Hearing

The parties expressed an intent to settle the matter out of court, and the tribunal adjourned the appeal to 20.11.2024.

21
Stage 2011/09/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the case for orders on 15.10.2024.

22
Stage 2108/08/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for a final hearing on 11.09.2024.

23
Stage 2210/07/2024

Hearing

The Tribunal granted a request from the respondent's counsel to reschedule the appeal for orders/hearing to 08.08.2024.

24
Stage 2313/05/2024

Hearing

The Tribunal noted that the appeal is ready for hearing and scheduled the matter for a hearing on 10.07.2024.

25
Stage 2410/04/2024

Hearing

No text available.

26
Stage 2522/03/2024

Hearing

The Tribunal granted an adjournment request from the respondent's counsel and scheduled the next hearing for 10.04.2024, noting that no further adjournments will be permitted.

27
Stage 2628/02/2024

Hearing

The Tribunal has ordered the appeal to be listed for a hearing on 22.03.2024.

28
Stage 2731/01/2024

Hearing

The Tribunal noted the absence of the respondent's counsel and scheduled the appeal for a hearing on 28.02.2024.

29
Stage 2819/01/2024

Hearing

The Tribunal fixed the next hearing date for Appeal-101/2019 to 31.01.2024 and directed that no further adjournments will be granted, noting that the matter will proceed based on available records if parties fail to appear.

30
Stage 2917/10/2023

Hearing

No text available.

31
Stage 3011/09/2023

Hearing

The Tribunal adjourned the proceedings and rescheduled the hearing for 17.10.2023 due to a strike called by the Bar Council of Uttar Pradesh.

32
Stage 3121/08/2023

Hearing

The Tribunal adjourned the appeal to 11.09.2023 due to the counsel for the appellant being on sanctioned leave, with a strict directive that no further adjournments will be granted on the next date.

33
Stage 3218/08/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to personal reasons, but warned that no further adjournments will be permitted and the case will proceed based on available records if counsel fails to appear on the next date.

34
Stage 3304/08/2023

Hearing

The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the hearing for 18.08.2023.

35
Stage 3424/05/2023

Hearing

No text available.

36
Stage 3521/04/2023

Hearing

The Tribunal granted the respondent counsel time to prepare his brief and scheduled the appeal for a hearing on 24.05.2023.

37
Stage 3614/03/2023

Hearing

The U.P. Real Estate Appellate Tribunal adjourned the proceedings due to the absence of the respondent's counsel and scheduled the appeal for a hearing on 21.04.2023.

38
Stage 3720/11/2021

Hearing

The Tribunal heard arguments regarding claims for delay penalties, super area discrepancies, and structural defects, subsequently directing both parties to exchange and file any additional material facts within 15 days and reserving the judgment.

39
Stage 3815/11/2021

Hearing

The Tribunal directed the parties to be prepared for the final hearing of the appeal scheduled for 20.11.2021, noting that no further adjournments will be granted on that date.

40
Stage 3921/10/2021

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the final hearing for 15.11.2021.

41
Stage 4013/09/2021

Hearing

The Tribunal granted an adjournment requested by the respondent and rescheduled the appeal for hearing on 21.10.2021.

42
Stage 4107/05/2021

Final Hearing

No text available.

43
Stage 4226/03/2021

Hearing

No text available.

44
Stage 4312/02/2021

Hearing

The Tribunal directed the Registry to record documents uploaded by the appellant and adjourned the matter to 26.03.2021 due to the absence of the respondent.

45
Stage 4408/01/2021

Hearing

No text available.

46
Stage 4518/12/2020

Hearing

No text available.

47
Stage 4605/11/2020

Hearing

No text available.

48
Stage 47Interim Order

Tribunal Order #0901126002252019-30-07-2025

The Tribunal directed the respondent/promoter to ensure the appellant or their tenant has unhindered ingress and egress to the unit, including the right to move goods and furniture in or out.

49
Stage 48Interim Order

Tribunal Order #0901126002252019-20-11-2021

The Tribunal heard arguments regarding claims for delay penalties, super area discrepancies, and structural defects, subsequently directing both parties to exchange and file any additional material facts within 15 days and reserving the judgment.

50
Stage 49Final Ruling Order

Tribunal Order #0901126002252019-02-12-2025

The Tribunal allowed the appeals, directing the respondent promoter to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal additional charges and enhanced super area payments with interest, and commence maintenance charges only from the date of physical possession.

51
Stage 50Interim Order

Tribunal Order #0901126002252019-14-07-2025

The Tribunal granted the respondent a one-week extension to comply with a previous order and directed the respondent promoter to provide all admissible maintenance services to the appellant, who is currently paying maintenance charges from the date of possession.

52
Stage 51Interim Order

Tribunal Order #0901126002252019-07-03-2025

The Tribunal directed the respondent to file an affidavit explaining the execution of additional FAR and ordered the appellant to deposit maintenance fees from the date of possession, pending the appeal outcome.

53
Stage 52Interim Order

Tribunal Order #0901126002252019-20-12-2024

The Tribunal directed the respondent/promoter to submit the super area computation and provide a categorical statement regarding compliance with building bye-laws, while scheduling the next hearing for January 24, 2025.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appeals, directing the respondent promoter to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal additional charges and enhanced super area payments with interest, and commence maintenance charges only from the date of physical possession. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appeals, directing the respondent promoter to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal additional charges and enhanced super area payments with interest, and commence maintenance charges only from the date of physical possession.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

w.e.f. 01.07.2016 to 08.12.2022

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Suchita Singh

Respondent Advocate(s)

  • Saurabh Misra
  • Shashank Kumar
  • Krishna Kumar Singh

Official RERA Tribunal Orders (6)

INTERIM_ORDEROrder ID: 0901126002252019-30-07-2025

The Tribunal directed the respondent/promoter to ensure the appellant or their tenant has unhindered ingress and egress to the unit, including the right to move goods and furniture in or out.

INTERIM_ORDEROrder ID: 0901126002252019-20-11-2021

The Tribunal heard arguments regarding claims for delay penalties, super area discrepancies, and structural defects, subsequently directing both parties to exchange and file any additional material facts within 15 days and reserving the judgment.

FINAL_ORDEROrder ID: 0901126002252019-02-12-2025

The Tribunal allowed the appeals, directing the respondent promoter to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal additional charges and enhanced super area payments with interest, and commence maintenance charges only from the date of physical possession.

INTERIM_ORDEROrder ID: 0901126002252019-14-07-2025

The Tribunal granted the respondent a one-week extension to comply with a previous order and directed the respondent promoter to provide all admissible maintenance services to the appellant, who is currently paying maintenance charges from the date of possession.

INTERIM_ORDEROrder ID: 0901126002252019-07-03-2025

The Tribunal directed the respondent to file an affidavit explaining the execution of additional FAR and ordered the appellant to deposit maintenance fees from the date of possession, pending the appeal outcome.

INTERIM_ORDEROrder ID: 0901126002252019-20-12-2024

The Tribunal directed the respondent/promoter to submit the super area computation and provide a categorical statement regarding compliance with building bye-laws, while scheduling the next hearing for January 24, 2025.

TathyaGrid RERA Intelligence AI

Need to research all rulings for paramount probuild pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →