Appellant / Complainant
Nishi Kant Rai
Respondent
Paramount Probuild Pvt. Ltd.
paramount probuild pvt. ltd.
₹4,51,956
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126003082019 by Nishi Kant Rai against Paramount Probuild Pvt. Ltd. before up_rera.
Part Heard
The Tribunal allowed the appeals, directing the respondent to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal charges totaling Rs. 1,65,374 and enhanced super area charges of Rs. 2,86,582 with interest, and to levy maintenance charges only from the date of physical possession (09.12.2022).
Further Hearing
The Tribunal has granted a request to list the appeal as a part-heard matter on 02.12.2025.
Further Hearing
The Tribunal granted a mutual request for adjournment from both parties and scheduled the case for orders on 27.11.2025, noting that no further adjournments will be permitted.
Further Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for orders/hearing on 13.11.2025, noting that no further adjournments will be permitted.
Further Hearing
The Tribunal heard arguments from both parties but found them inconclusive, resulting in the appeal being adjourned for further hearing on 03.11.2025.
Further Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 09.10.2025.
Further Hearing
The Tribunal granted an adjournment requested by the respondent and scheduled the case for orders on 09.09.2025, noting that no further adjournments will be permitted.
Further Hearing
The Tribunal granted the respondent time to upload documents regarding disputed charges and adjourned the matter to 27.08.2025 for further hearing or orders.
Further Hearing
The Tribunal directed the respondent/promoter not to impede the appellant or their tenant's ingress/egress and confirmed the appellant's right to move goods and furniture in or out of the unit.
Further Hearing
The Tribunal granted the respondent a one-week extension to comply with a previous order and directed the respondent promoter to provide all admissible maintenance services to the appellant, who is currently paying maintenance charges from the date of possession.
Further Hearing
The Tribunal granted the respondent additional time to comply with the previous order dated 07.03.2025 and scheduled the case for orders on 14.07.2025.
Further Hearing
The Tribunal granted a request from the respondent's counsel to adjourn the matter to 21.05.2025 and permitted the parties to exchange pleadings in the interim.
Further Hearing
The Tribunal granted the appellant's counsel additional time to comply with a previous order and scheduled the case for hearing on April 30, 2025.
Further Hearing
The Tribunal directed the respondent to file an affidavit explaining the execution of additional FAR granted by the Greater Noida Authority and ordered the appellant to deposit maintenance fees from the date of possession.
Further Hearing
The Tribunal has granted a request from the respondent's counsel to list the appeal for a hearing on 07.03.2025.
Further Hearing
The Tribunal noted the presence of the appellant's counsel and the absence of the respondent's counsel, subsequently listing the matter for orders on 12.02.2025.
Further Hearing
The Tribunal directed the respondent/promoter to submit the super area computation and provide a categorical statement regarding compliance with building bye-laws following the purchase of additional F.A.R.
Further Hearing
The tribunal adjourned the proceedings upon a request from the respondent's counsel and rescheduled the hearing for December 20, 2024, noting that no further adjournments will be granted.
Hearing
The Tribunal noted the parties' intention to attempt an out-of-court settlement and adjourned the appeal to 20.11.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to the senior counsel being out of station and listed the case for orders on 15.10.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for a final hearing on 11.09.2024.
Hearing
The Tribunal granted a request from the respondent's counsel to adjourn the matter and rescheduled the appeal for orders/hearing on 08.08.2024.
Hearing
The Tribunal noted that the appeal is ready for hearing and scheduled the matter for a hearing on 10.07.2024.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to a conflict in the High Court, scheduling the next hearing for 10.04.2024 with a warning that no further adjournments will be permitted.
Hearing
The Tribunal has ordered the appeal to be listed for a hearing on 22.03.2024.
Hearing
The Tribunal noted the absence of the respondent's counsel due to being held up in the High Court and rescheduled the hearing for 28.02.2024.
Hearing
The Tribunal fixed the next hearing date for the appeal to 31.01.2024 and directed that no further adjournments will be granted, noting that the matter will proceed based on available records if parties fail to appear.
Hearing
The Tribunal adjourned the proceedings and rescheduled the hearing for 17.10.2023 due to a call by the Bar Council of Uttar Pradesh for lawyers to abstain from judicial work.
Hearing
The Tribunal adjourned the appeal to 11.09.2023 due to the appellant's counsel being on leave, with a strict directive that no further adjournments will be granted on the next date.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to personal reasons, but cautioned that no further adjournments will be permitted and the case will proceed based on available records if counsel fails to appear on the next date.
Hearing
The Tribunal adjourned the matter and rescheduled the hearing for 18.08.2023 at the request of the appellant's counsel due to the absence of the respondent's counsel.
Hearing
The Tribunal noted the filing of the respondent's Vakalatnama and adjourned the matter to 24.05.2023 for hearing following the exchange of pleadings.
Hearing
The Tribunal adjourned the proceedings due to the absence of the respondent's counsel and scheduled the appeal for a hearing on 21.04.2023.
Hearing
The Tribunal heard arguments regarding claims of delayed possession, super area discrepancies, and structural defects, and directed both parties to exchange and file any additional material facts within 15 days, reserving the judgment.
Hearing
The Tribunal directed the parties to appear prepared for the final hearing scheduled for 20.11.2021 and noted that no further adjournments would be granted on that date.
Hearing
The Tribunal granted an adjournment request made by the appellant's counsel due to illness and rescheduled the final hearing for 15.11.2021.
Hearing
The Tribunal granted an adjournment requested by the respondent and rescheduled the appeal for hearing on 21.10.2021.
Hearing
The Tribunal adjourned the matter to 26.03.2021 after declining to pass interim orders regarding construction defects in the absence of the respondent.
Tribunal Order #0901126003082019-30-07-2025
The Tribunal directed the respondent/promoter not to impede the appellant or their tenant's ingress/egress and confirmed the appellant's right to move goods and furniture in or out of the unit.
Tribunal Order #0901126003082019-14-07-2025
The Tribunal granted the respondent a one-week extension to comply with a previous order and directed the respondent promoter to provide all admissible maintenance services to the appellant, who is currently paying maintenance charges from the date of possession.
Tribunal Order #0901126003082019-07-03-2025
The Tribunal directed the respondent to file an affidavit explaining the execution of additional FAR granted by the Greater Noida Authority and ordered the appellant to deposit maintenance fees from the date of possession.
Tribunal Order #0901126003082019-20-12-2024
The Tribunal directed the respondent/promoter to submit the super area computation and provide a categorical statement regarding compliance with building bye-laws following the purchase of additional F.A.R.
Tribunal Order #0901126003082019-20-11-2021
The Tribunal heard arguments regarding claims of delayed possession, super area discrepancies, and structural defects, and directed both parties to exchange and file any additional material facts within 15 days, reserving the judgment.
Tribunal Order #0901126003082019-02-12-2025
The Tribunal allowed the appeals, directing the respondent to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal charges totaling Rs. 1,65,374 and enhanced super area charges of Rs. 2,86,582 with interest, and to levy maintenance charges only from the date of physical possession (09.12.2022).
Tribunal Disposal & Final Award Ruling
The Tribunal allowed the appeals, directing the respondent to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal charges totaling Rs. 1,65,374 and enhanced super area charges of Rs. 2,86,582 with interest, and to levy maintenance charges only from the date of physical possession (09.12.2022). Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal allowed the appeals, directing the respondent to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal charges totaling Rs. 1,65,374 and enhanced super area charges of Rs. 2,86,582 with interest, and to levy maintenance charges only from the date of physical possession (09.12.2022).
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR + 1%
Interest Period
w.e.f. 01.07.2016 to 08.12.2022
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Suchita Singh
Respondent Advocate(s)
- Shashank Kumar
Official RERA Tribunal Orders (6)
The Tribunal directed the respondent/promoter not to impede the appellant or their tenant's ingress/egress and confirmed the appellant's right to move goods and furniture in or out of the unit.
The Tribunal granted the respondent a one-week extension to comply with a previous order and directed the respondent promoter to provide all admissible maintenance services to the appellant, who is currently paying maintenance charges from the date of possession.
The Tribunal directed the respondent to file an affidavit explaining the execution of additional FAR granted by the Greater Noida Authority and ordered the appellant to deposit maintenance fees from the date of possession.
The Tribunal directed the respondent/promoter to submit the super area computation and provide a categorical statement regarding compliance with building bye-laws following the purchase of additional F.A.R.
The Tribunal heard arguments regarding claims of delayed possession, super area discrepancies, and structural defects, and directed both parties to exchange and file any additional material facts within 15 days, reserving the judgment.
The Tribunal allowed the appeals, directing the respondent to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal charges totaling Rs. 1,65,374 and enhanced super area charges of Rs. 2,86,582 with interest, and to levy maintenance charges only from the date of physical possession (09.12.2022).
Need to research all rulings for paramount probuild pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.