up_reraStatus: Completed
CASE ID: 0901126003572019

Appellant / Complainant

Devendra Nath, Archana Pandey

VS

Respondent

Panchsheel Buildtech Pvt. Ltd.

Developer Firm

panchsheel buildtech pvt. ltd.

Disputed Amount

23,48,093

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

8 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003572019 by Devendra Nath, Archana Pandey against Panchsheel Buildtech Pvt. Ltd. before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 126/11/2021

for delivery of Judgment/Order

The Tribunal confirmed the Regulatory Authority's order directing the respondent to pay interest at MCLR+1% for delayed possession, while rejecting the appellants' request for a full refund due to the lack of inordinate delay.

3
Stage 224/03/2021

Judgement

The Tribunal directed the respondent to file a board resolution and authorized signatory ID within three days and ordered both parties to submit lists of dates and relied-upon judgments within a week.

4
Stage 312/02/2021

Further Hearing

The Tribunal directed the parties to file a concise list of dates, events, and relied-upon judgments within one week and exchange them via email before the next hearing. The matter is scheduled for judgment on 24.03.2021.

5
Stage 421/01/2021

Hearing on Appeal

The Tribunal directed the respondent's counsel to file a vakalatnama with required documents within three days and ordered both parties to submit a concise list of dates and events along with relied-upon judgments.

6
Stage 507/10/2020

Hearing on Appeal

No text available.

7
Stage 6Final Ruling Order

Tribunal Order #0901126003572019-26-11-2021

The Tribunal confirmed the Regulatory Authority's order directing the respondent to pay interest at MCLR+1% for delayed possession, while rejecting the appellants' request for a full refund due to the lack of inordinate delay.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal confirmed the Regulatory Authority's order directing the respondent to pay interest at MCLR+1% for delayed possession, while rejecting the appellants' request for a full refund due to the lack of inordinate delay. Awarded in favor of Partial. Awarded interest rate: MCLR + 1%.

Disposal Winner: PartialInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal confirmed the Regulatory Authority's order directing the respondent to pay interest at MCLR+1% for delayed possession, while rejecting the appellants' request for a full refund due to the lack of inordinate delay.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR + 1%

Interest Period

w.e.f. 24.02.2017 till the date of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey

Respondent Advocate(s)

  • R.D. Kranti

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126003572019-26-11-2021

The Tribunal confirmed the Regulatory Authority's order directing the respondent to pay interest at MCLR+1% for delayed possession, while rejecting the appellants' request for a full refund due to the lack of inordinate delay.

TathyaGrid RERA Intelligence AI

Need to research all rulings for panchsheel buildtech pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →