Appellant / Complainant
Ratan Buildtech Private Limited
Respondent
Y D Sharma
ratan buildtech private limited
₹7,49,595
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126019562022 by Ratan Buildtech Private Limited against Y D Sharma before up_rera.
Delay condonation
The Tribunal dismissed the appeal filed by Ratan Buildtech Pvt. Ltd., upholding a penalty of Rs. 7,49,595 imposed for failure to comply with a possession order and directing the payment of the penalty and costs.
Delay condonation
The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000 to be paid for legal library books and clarified that no further adjournments will be permitted.
Delay condonation
The Tribunal adjourned the appeal at the request of the appellant's counsel and scheduled the matter for orders/hearing on 19.02.2025.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 30.01.2025, noting that no further adjournments will be permitted.
Delay condonation
The Tribunal adjourned the proceedings following an adjournment application by the appellant's counsel and scheduled the matter for hearing on the application for condonation of delay on 16.01.2025.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for November 28, 2024, noting that no further adjournments will be permitted.
Delay condonation
The Tribunal granted a request from the applicant's counsel to adjourn the matter, rescheduling the case for orders/hearing on 16.09.2024.
Hearing
The Tribunal noted the absence of the respondent's counsel and adjourned the appeal to 14.08.2024 for hearing.
Hearing
The Tribunal granted an adjournment request made by the appellant's counsel and rescheduled the appeal for hearing on 16.05.2024.
Hearing
The Tribunal granted an adjournment following a request from the applicant's counsel on health grounds and rescheduled the hearing for consideration of the condonation of delay application to 16.04.2024.
Hearing
The Tribunal granted an adjournment to the appellant's counsel to prepare their brief and scheduled the hearing for March 12, 2024.
Hearing
The Tribunal adjourned the proceedings due to the illness of the appellant's counsel and granted a final 10-day extension for the applicant to file a reply to the respondent's objections.
Further Order
The Tribunal granted the applicant one week's time to file a reply against the objections previously filed by RERA.
Further Order
The Tribunal noted that ex-parte proceedings have been initiated against respondent No. 2 and scheduled the case for further orders on 13.01.2023.
For Order
The Tribunal decided to proceed ex-parte against Respondent No. 2 due to non-appearance and granted respondents a final opportunity to file their reply before the next hearing on 09.12.2022.
For Order
The Tribunal noted the service of notice to Respondent No. 2 via affidavit and directed the respondent to file a reply to the grounds of appeal before the next hearing on 09.11.2022.
For Order
The Tribunal scheduled the case for September 9, 2022, to consider an application for condonation of delay and directed the applicant's counsel to file an affidavit of service regarding respondent no. 2.
Hearing
The Tribunal issued notice to the respondent and directed the appellant to serve the notice via speed post and file an affidavit of service before the next hearing on 10.08.2022.
Hearing
The Tribunal allowed an application to amend the relief clause of the appeal and directed the appellant to upload the amended memo within two days, subsequently listing the matter for 14.07.2022.
Defect Removal
The Tribunal granted the applicant three days to file an application for amending the prayer clauses of the appeal due to defects in the original filing and scheduled the matter for July 7, 2022.
Tribunal Order #0901126019562022-17-03-2025
The Tribunal dismissed the appeal filed by Ratan Buildtech Pvt. Ltd., upholding a penalty of Rs. 7,49,595 imposed for failure to comply with a possession order and directing the payment of the penalty and costs.
Tribunal Order #0901126019562022-19-02-2025
The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000 to be paid for legal library books and clarified that no further adjournments will be permitted.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal filed by Ratan Buildtech Pvt. Ltd., upholding a penalty of Rs. 7,49,595 imposed for failure to comply with a possession order and directing the payment of the penalty and costs. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal filed by Ratan Buildtech Pvt. Ltd., upholding a penalty of Rs. 7,49,595 imposed for failure to comply with a possession order and directing the payment of the penalty and costs.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Ankit Raj Chaudhary
- Mahima Pahwa
- Praneti Agarwal
- Deepak Agarwal
- Unnati Vijay
Respondent Advocate(s)
- Shobhit Mohan Shukla
Official RERA Tribunal Orders (2)
The Tribunal dismissed the appeal filed by Ratan Buildtech Pvt. Ltd., upholding a penalty of Rs. 7,49,595 imposed for failure to comply with a possession order and directing the payment of the penalty and costs.
The Tribunal granted an adjournment to the appellant subject to a cost of Rs. 25,000 to be paid for legal library books and clarified that no further adjournments will be permitted.
Need to research all rulings for ratan buildtech private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.