CASE ID: 0901126022872023

Appellant / Complainant

Ratan Buildtech Private Limited

VS

Respondent

Nishant Dang

Developer Firm

ratan buildtech private limited

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

22 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126022872023 by Ratan Buildtech Private Limited against Nishant Dang before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 114/05/2025

Hearing

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly awarded delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 26.09.2022, excluding a six-month COVID-19 force majeure period.

3
Stage 221/04/2025

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel but explicitly ruled that no further adjournments will be permitted and directed that alternative arrangements must be made if the counsel cannot appear on the next date.

4
Stage 321/03/2025

Hearing

Upon joint request of the parties, the matter is adjourned for orders on 21.04.2025.

5
Stage 428/02/2025

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for March 21, 2025, noting that no further adjournments will be permitted.

6
Stage 505/02/2025

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to personal illness and rescheduled the hearing for February 28, 2025.

7
Stage 624/09/2024

for delivery of Judgment/Order

The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that since the impugned orders prima facie appeared to be passed without jurisdiction regarding interest rates, the delay should be excused to allow for a merit-based adjudication.

8
Stage 714/08/2024

Delay condonation

The Tribunal heard arguments regarding an application for condonation of delay and has reserved its order on the matter.

9
Stage 816/07/2024

Hearing

The Tribunal has scheduled the appeal for orders or hearing on 14.08.2024, referring to a previous order passed in Appeal No. 260/2023.

10
Stage 916/05/2024

Hearing

No text available.

11
Stage 1010/05/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to a medical exigency and rescheduled the hearing for 16.05.2024.

12
Stage 1124/04/2024

Hearing

The Tribunal noted that pleadings have been exchanged and the appeal is ripe for hearing; consequently, the matter is listed for orders/hearing on 10.05.2024.

13
Stage 1229/03/2024

Hearing

The Tribunal refers the parties to a previous order passed in Appeal No. D382/2023 for further directions.

14
Stage 1315/03/2024

Hearing

The Tribunal granted an adjournment to the appellant's counsel to rectify potential deficiencies in compliance with Section 43(5) of the Act and scheduled the matter for hearing on March 29, 2024.

15
Stage 1413/02/2024

Hearing

The Tribunal noted that the appeal is ready for hearing and scheduled it for 15.03.2024 to consider the application for condonation of delay.

16
Stage 1516/01/2024

Hearing

The Tribunal has adjourned the defective appeal to 13.02.2024 for consideration of the application for condonation of delay, following a joint request from both parties' counsel.

17
Stage 1612/10/2023

Hearing

No text available.

18
Stage 1704/09/2023

Notice

The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the defective appeal for consideration on 12.10.2023.

19
Stage 1813/07/2023

Delay condonation

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and scheduled the matter for hearing on 04.09.2023.

20
Stage 19Final Ruling Order

Tribunal Order #0901126022872023-14-05-2025

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly awarded delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 26.09.2022, excluding a six-month COVID-19 force majeure period.

21
Stage 20Interim Order

Tribunal Order #0901126022872023-24-09-2024

The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that since the impugned orders prima facie appeared to be passed without jurisdiction regarding interest rates, the delay should be excused to allow for a merit-based adjudication.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly awarded delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 26.09.2022, excluding a six-month COVID-19 force majeure period. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.

Disposal Winner: PartialInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly awarded delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 26.09.2022, excluding a six-month COVID-19 force majeure period.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.01.2020 to 26.09.2022 (excluding six months force majeure period for Covid-19)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Mahima Pahwa

Respondent Advocate(s)

  • Raj Singh
  • Suryansh Narula

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126022872023-14-05-2025

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly awarded delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 26.09.2022, excluding a six-month COVID-19 force majeure period.

INTERIM_ORDEROrder ID: 0901126022872023-24-09-2024

The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that since the impugned orders prima facie appeared to be passed without jurisdiction regarding interest rates, the delay should be excused to allow for a merit-based adjudication.

TathyaGrid RERA Intelligence AI