Appellant / Complainant
Ratan Buildtech Private Limited
Respondent
Nishant Dang
ratan buildtech private limited
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126022872023 by Ratan Buildtech Private Limited against Nishant Dang before up_rera.
Hearing
The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly awarded delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 26.09.2022, excluding a six-month COVID-19 force majeure period.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel but explicitly ruled that no further adjournments will be permitted and directed that alternative arrangements must be made if the counsel cannot appear on the next date.
Hearing
Upon joint request of the parties, the matter is adjourned for orders on 21.04.2025.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for March 21, 2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to personal illness and rescheduled the hearing for February 28, 2025.
for delivery of Judgment/Order
The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that since the impugned orders prima facie appeared to be passed without jurisdiction regarding interest rates, the delay should be excused to allow for a merit-based adjudication.
Delay condonation
The Tribunal heard arguments regarding an application for condonation of delay and has reserved its order on the matter.
Hearing
The Tribunal has scheduled the appeal for orders or hearing on 14.08.2024, referring to a previous order passed in Appeal No. 260/2023.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to a medical exigency and rescheduled the hearing for 16.05.2024.
Hearing
The Tribunal noted that pleadings have been exchanged and the appeal is ripe for hearing; consequently, the matter is listed for orders/hearing on 10.05.2024.
Hearing
The Tribunal refers the parties to a previous order passed in Appeal No. D382/2023 for further directions.
Hearing
The Tribunal granted an adjournment to the appellant's counsel to rectify potential deficiencies in compliance with Section 43(5) of the Act and scheduled the matter for hearing on March 29, 2024.
Hearing
The Tribunal noted that the appeal is ready for hearing and scheduled it for 15.03.2024 to consider the application for condonation of delay.
Hearing
The Tribunal has adjourned the defective appeal to 13.02.2024 for consideration of the application for condonation of delay, following a joint request from both parties' counsel.
Notice
The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the defective appeal for consideration on 12.10.2023.
Delay condonation
The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and scheduled the matter for hearing on 04.09.2023.
Tribunal Order #0901126022872023-14-05-2025
The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly awarded delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 26.09.2022, excluding a six-month COVID-19 force majeure period.
Tribunal Order #0901126022872023-24-09-2024
The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that since the impugned orders prima facie appeared to be passed without jurisdiction regarding interest rates, the delay should be excused to allow for a merit-based adjudication.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly awarded delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 26.09.2022, excluding a six-month COVID-19 force majeure period. Awarded in favor of Partial. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly awarded delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 26.09.2022, excluding a six-month COVID-19 force majeure period.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR+1%
Interest Period
from 01.01.2020 to 26.09.2022 (excluding six months force majeure period for Covid-19)
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Mahima Pahwa
Respondent Advocate(s)
- Raj Singh
- Suryansh Narula
Official RERA Tribunal Orders (2)
The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but directly awarded delay interest to the respondent at MCLR+1% for the period from 01.01.2020 to 26.09.2022, excluding a six-month COVID-19 force majeure period.
The Tribunal condoned the delay in filing 12 appeals by Ratan Buildtech Pvt. Ltd., ruling that since the impugned orders prima facie appeared to be passed without jurisdiction regarding interest rates, the delay should be excused to allow for a merit-based adjudication.
Need to research all rulings for ratan buildtech private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.