Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126003762019 by Sahara Prime City Limited, Usha Rani Singh against Usha Rani Singh before up_rera.

Non-Compliance & Execution
2
Stage 101/11/2021

Final Hearing

The Tribunal dismissed the appeal as not pressed upon the appellant's request and directed that the amount deposited under Section 43(5) of the Act be transferred to RERA for disbursement to the respondent.

3
Stage 228/10/2021

Hearing

The Tribunal granted the appellant's counsel additional time to seek instructions regarding the status of an Occupancy Certificate (OC) application and adjourned the matter to 01.11.2021.

4
Stage 328/09/2021

Hearing on Amendment Application

The Tribunal granted the respondent an extension of one week to file objections to the appellant's application for amendment and scheduled the next hearing for October 28, 2021.

5
Stage 415/04/2021

Hearing on Amendment Application

No text available.

6
Stage 524/03/2021

Hearing on Amendment Application

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for 15.04.2021.

7
Stage 617/03/2021

Compliance of section 43(5)

The Tribunal directed the Registry to locate a missing amendment application and ordered the appellant to ensure compliance with Section 43(5) of the RERA Act, 2016, pending the hearing on the amendment.

8
Stage 725/02/2021

Hearing

The Tribunal directed the appellant, M/S Sahara Prime City Limited, to ensure full compliance with Section 43(5) of the Act, 2016, by depositing the remaining required amount within 10 days.

9
Stage 808/02/2021

For Order

The Tribunal directed the Registry to record Sri Surendra Kumar Mishra as counsel for the appellant and adjourned the appeal to 25.02.2021 at the request of the appellant's counsel.

10
Stage 905/02/2021

Final Hearing

The Tribunal granted a request by the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 08.02.2021.

11
Stage 1005/01/2021

Hearing

No text available.

12
Stage 1101/12/2020

Hearing

No text available.

13
Stage 12Final Ruling Order

Tribunal Order #0901126003762019-01-11-2021

The Tribunal dismissed the appeal as not pressed upon the appellant's request and directed that the amount deposited under Section 43(5) of the Act be transferred to RERA for disbursement to the respondent.

14
Stage 13Interim Order

Tribunal Order #0901126003762019-17-03-2021

The Tribunal directed the Registry to locate a missing amendment application and ordered the appellant to ensure compliance with Section 43(5) of the RERA Act, 2016, pending the hearing on the amendment.

15
Stage 14Interim Order

Tribunal Order #0901126003762019-25-02-2021

The Tribunal directed the appellant, M/S Sahara Prime City Limited, to ensure full compliance with Section 43(5) of the Act, 2016, by depositing the remaining required amount within 10 days.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal as not pressed upon the appellant's request and directed that the amount deposited under Section 43(5) of the Act be transferred to RERA for disbursement to the respondent. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal as not pressed upon the appellant's request and directed that the amount deposited under Section 43(5) of the Act be transferred to RERA for disbursement to the respondent.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Surendra Kumar Mishra

Respondent Advocate(s)

  • Pranshu Agarwal

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126003762019-01-11-2021

The Tribunal dismissed the appeal as not pressed upon the appellant's request and directed that the amount deposited under Section 43(5) of the Act be transferred to RERA for disbursement to the respondent.

INTERIM_ORDEROrder ID: 0901126003762019-17-03-2021

The Tribunal directed the Registry to locate a missing amendment application and ordered the appellant to ensure compliance with Section 43(5) of the RERA Act, 2016, pending the hearing on the amendment.

INTERIM_ORDEROrder ID: 0901126003762019-25-02-2021

The Tribunal directed the appellant, M/S Sahara Prime City Limited, to ensure full compliance with Section 43(5) of the Act, 2016, by depositing the remaining required amount within 10 days.