Appellant / Complainant
Sunita Agrawal
Respondent
Sahara Prime City Limited
sahara prime city limited
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126015862021 by Sunita Agrawal against Sahara Prime City Limited before up_rera.
Hearing
The appeal was dismissed for want of prosecution as neither the appellant nor the respondent appeared before the Tribunal.
Hearing
The Tribunal adjourned the proceedings to 24.04.2023 following an update that the parties are in the process of an amicable settlement regarding a discrepancy in deposited amounts.
Hearing
The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the matter for orders on 03.02.2023.
Hearing
The Tribunal adjourned the appeal due to the absence of parties and scheduled the matter for a hearing on 02.01.2023.
Hearing
The Tribunal directed the appellant to upload their statement of account on the e-Portal and ordered the respondent to pay the remaining principal amount and file an interest payment schedule before the next hearing.
Hearing
The Tribunal noted the absence of both parties and observed that the matter may have been settled; consequently, the case is adjourned to 07.11.2022 with a direction for both parties to appear.
Hearing
The Tribunal noted the partial settlement of dues between the parties and directed the appellant to provide an account statement to the respondent, while ordering the respondent to pay any remaining balance and agreed interest as per the settlement terms.
Hearing
The Tribunal directed a counsel to file a response as previously ordered and noted that the respondent committed to paying the remaining balance due to the appellant before the next hearing date.
Hearing
The Tribunal directed the respondent, M/s. Sahara Prime City Limited, to pay the remaining balance amount to the appellant within 10 days.
Hearing
The Respondent (Sahara Prime City Limited) reported a partial payment of Rs. 10,00,000 via cheque to the Appellant and committed to paying the remaining balance by the next hearing date.
Exchange of pleadings
The Tribunal stayed the operation of the Regulatory Authority's order dated 27.10.2020 and directed the Secretary, RERA to explain under which legal provision the Authority can modify an original order during execution proceedings.
Exchange of pleadings
The Tribunal directed the respondent-builder to refund the principal amount in two installments and the interest amount in three installments, with the case listed for further orders on 05.04.2022.
Exchange of pleadings
The Tribunal has adjourned the matter and scheduled the case for further orders on 27.01.2022.
Further Order
The Tribunal noted the respondent's reply to the grounds of appeal and the appellant's decision not to file a rejoinder; the case is adjourned to 05.01.2022.
Delay condonation
The Tribunal allowed the application for condonation of delay, citing the Supreme Court's relaxation due to the COVID-19 pandemic, and ordered the defective appeal to be registered as a Regular Appeal.
Delay condonation
The Tribunal granted the respondent a 10-day extension to file objections to the application for condonation of delay and the grounds of appeal, noting that failure to appear or file may result in ex-parte proceedings.
Delay condonation
The Tribunal issued notice to the respondent regarding an application for condonation of delay and directed the parties to exchange objections and replies via e-mail and the e-portal before the next hearing on 24.03.2021.
Tribunal Order #0901126015862021-22-09-2022
The Tribunal noted the partial settlement of dues between the parties and directed the appellant to provide an account statement to the respondent, while ordering the respondent to pay any remaining balance and agreed interest as per the settlement terms.
Tribunal Order #0901126015862021-20-05-2022
The Tribunal directed the respondent, M/s. Sahara Prime City Limited, to pay the remaining balance amount to the appellant within 10 days.
Tribunal Order #0901126015862021-05-04-2022
The Tribunal stayed the operation of the Regulatory Authority's order dated 27.10.2020 and directed the Secretary, RERA to explain under which legal provision the Authority can modify an original order during execution proceedings.
Tribunal Order #0901126015862021-09-03-2022
The Tribunal directed the respondent-builder to refund the principal amount in two installments and the interest amount in three installments, with the case listed for further orders on 05.04.2022.
Tribunal Order #0901126015862021-07-11-2022
The Tribunal directed the appellant to upload their statement of account on the e-Portal and ordered the respondent to pay the remaining principal amount and file an interest payment schedule before the next hearing.
Tribunal Order #0901126015862021-25-08-2022
The Tribunal directed a counsel to file a response as previously ordered and noted that the respondent committed to paying the remaining balance due to the appellant before the next hearing date.
Tribunal Order #0901126015862021-18-04-2022
The Respondent (Sahara Prime City Limited) reported a partial payment of Rs. 10,00,000 via cheque to the Appellant and committed to paying the remaining balance by the next hearing date.
Tribunal Order #0901126015862021-09-11-2021
The Tribunal allowed the application for condonation of delay, citing the Supreme Court's relaxation due to the COVID-19 pandemic, and ordered the defective appeal to be registered as a Regular Appeal.
Tribunal Disposal & Final Award Ruling
Dismissed Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Vipin Verma
Respondent Advocate(s)
- Surendra Kumar Mishra
Official RERA Tribunal Orders (8)
The Tribunal noted the partial settlement of dues between the parties and directed the appellant to provide an account statement to the respondent, while ordering the respondent to pay any remaining balance and agreed interest as per the settlement terms.
The Tribunal directed the respondent, M/s. Sahara Prime City Limited, to pay the remaining balance amount to the appellant within 10 days.
The Tribunal stayed the operation of the Regulatory Authority's order dated 27.10.2020 and directed the Secretary, RERA to explain under which legal provision the Authority can modify an original order during execution proceedings.
The Tribunal directed the respondent-builder to refund the principal amount in two installments and the interest amount in three installments, with the case listed for further orders on 05.04.2022.
The Tribunal directed the appellant to upload their statement of account on the e-Portal and ordered the respondent to pay the remaining principal amount and file an interest payment schedule before the next hearing.
The Tribunal directed a counsel to file a response as previously ordered and noted that the respondent committed to paying the remaining balance due to the appellant before the next hearing date.
The Respondent (Sahara Prime City Limited) reported a partial payment of Rs. 10,00,000 via cheque to the Appellant and committed to paying the remaining balance by the next hearing date.
The Tribunal allowed the application for condonation of delay, citing the Supreme Court's relaxation due to the COVID-19 pandemic, and ordered the defective appeal to be registered as a Regular Appeal.
Need to research all rulings for sahara prime city limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.