up_reraStatus: Completed
CASE ID: 0901126016222021

Appellant / Complainant

Gouri Garg

VS

Respondent

Sahara Prime City Limited

Developer Firm

sahara prime city limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

30 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126016222021 by Gouri Garg against Sahara Prime City Limited before up_rera.

2
Stage 124/04/2023

For Order

The appeal was dismissed for want of prosecution as neither party appeared before the Tribunal and no request for adjournment was received.

3
Stage 214/03/2023

For Order

The Tribunal adjourned the proceedings to 24.04.2023 following a submission that the parties are in the process of an amicable settlement regarding the disputed amount.

4
Stage 303/02/2023

For Order

No text available.

5
Stage 402/01/2023

Further Order

The court noted the absence of both parties and directed them to comply with a previous order dated 27.11.2022 within 10 days, adjourning the matter to 03.02.2023.

6
Stage 501/12/2022

Further Order

This text represents the header/caption of an appeal filed by Gouri Garg against Sahara Prime City Limited before the U.P. Real Estate Appellate Tribunal; no substantive ruling or directive is contained in this excerpt.

7
Stage 607/11/2022

Further Order

The Tribunal directed the appellant to upload their statement of account on the e-Portal and ordered the respondent to pay the remaining principal amount and file an interest payment schedule before the next hearing.

8
Stage 712/10/2022

Further Order

The Tribunal directed the appellant to submit an account statement via email to the respondent and ordered the respondent to pay any remaining balance due to the appellant.

9
Stage 822/09/2022

Further Order

The Tribunal noted the partial settlement of dues between the parties and directed the appellant to provide an account statement to the respondent, who is ordered to pay any remaining balance plus agreed interest.

10
Stage 925/08/2022

Further Order

The Tribunal noted the receipt of a second installment of Rs. 10 lacs by the appellant and scheduled the matter for further orders on 22.09.2022.

11
Stage 1029/07/2022

Further Order

No text available.

12
Stage 1104/07/2022

Further Order

The tribunal granted a short adjournment requested by the respondent's counsel due to an inability to pay the remaining amount, listing the case for further orders on 29.07.2022.

13
Stage 1220/05/2022

Further Order

The Tribunal granted a request for adjournment made by the respondent's counsel and rescheduled the appeal for hearing on 04.07.2022.

14
Stage 1322/04/2022

Further Order

The respondent submitted a cheque of Rs. 10,00,000/- toward the appellant and undertook to pay the remaining principal amount and interest by the next hearing date.

15
Stage 1405/04/2022

Further Order

The tribunal adjourned the matter to 22.04.2022 due to the absence of the respondent's counsel, noting a subsequent submission by the respondent regarding an intent to pay the appellant in installments.

16
Stage 1509/03/2022

Further Order

The Tribunal recorded the respondent-builder's willingness to refund the amount in installments and directed the respondent to clarify the installment schedule, while noting the appellant's preference for receiving principal and interest in separate installment structures.

17
Stage 1605/01/2022

Further Order

The Tribunal heard arguments regarding the alleged modification of a previous order by the Regulatory Authority and granted the respondent a short adjournment to seek instructions on compliance, listing the matter for 27.01.2022.

18
Stage 1702/12/2021

Further Order

This is a procedural entry recording the appearance of counsel for both the appellant (Gouri Garg) and the respondent (Sahara Prime City Limited) before the Division Bench.

19
Stage 1809/11/2021

Delay condonation

The Tribunal allowed the application for condonation of delay by applying the Supreme Court's relaxation period due to the COVID-19 pandemic, thereby converting the defective appeal into a regular appeal.

20
Stage 1906/10/2021

Delay condonation

The Tribunal issued fresh notice to the respondent due to previous non-service during lockdown and directed the parties to exchange pleadings via email and upload them to the e-portal before the next hearing on 09.11.2021.

21
Stage 2020/04/2021

Delay condonation

No text available.

22
Stage 2124/03/2021

Notice

No text available.

23
Stage 2201/03/2021

Delay condonation

The Tribunal issued notice to the respondent regarding an application for condonation of delay and established a timeline for the exchange of pleadings via email and the e-portal.

24
Stage 23Interim Order

Tribunal Order #0901126016222021-12-10-2022

The Tribunal directed the appellant to submit an account statement via email to the respondent and ordered the respondent to pay any remaining balance due to the appellant.

25
Stage 24Interim Order

Tribunal Order #0901126016222021-22-04-2022

The respondent submitted a cheque of Rs. 10,00,000/- toward the appellant and undertook to pay the remaining principal amount and interest by the next hearing date.

26
Stage 25Interim Order

Tribunal Order #0901126016222021-09-11-2021

The Tribunal allowed the application for condonation of delay by applying the Supreme Court's relaxation period due to the COVID-19 pandemic, thereby converting the defective appeal into a regular appeal.

27
Stage 26Interim Order

Tribunal Order #0901126016222021-07-11-2022

The Tribunal directed the appellant to upload their statement of account on the e-Portal and ordered the respondent to pay the remaining principal amount and file an interest payment schedule before the next hearing.

28
Stage 27Interim Order

Tribunal Order #0901126016222021-22-09-2022

The Tribunal noted the partial settlement of dues between the parties and directed the appellant to provide an account statement to the respondent, who is ordered to pay any remaining balance plus agreed interest.

29
Stage 28Interim Order

Tribunal Order #0901126016222021-09-03-2022

The Tribunal recorded the respondent-builder's willingness to refund the amount in installments and directed the respondent to clarify the installment schedule, while noting the appellant's preference for receiving principal and interest in separate installment structures.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vipin Verma

Respondent Advocate(s)

  • Surendra Kumar Mishra

Official RERA Tribunal Orders (6)

INTERIM_ORDEROrder ID: 0901126016222021-12-10-2022

The Tribunal directed the appellant to submit an account statement via email to the respondent and ordered the respondent to pay any remaining balance due to the appellant.

INTERIM_ORDEROrder ID: 0901126016222021-22-04-2022

The respondent submitted a cheque of Rs. 10,00,000/- toward the appellant and undertook to pay the remaining principal amount and interest by the next hearing date.

INTERIM_ORDEROrder ID: 0901126016222021-09-11-2021

The Tribunal allowed the application for condonation of delay by applying the Supreme Court's relaxation period due to the COVID-19 pandemic, thereby converting the defective appeal into a regular appeal.

INTERIM_ORDEROrder ID: 0901126016222021-07-11-2022

The Tribunal directed the appellant to upload their statement of account on the e-Portal and ordered the respondent to pay the remaining principal amount and file an interest payment schedule before the next hearing.

INTERIM_ORDEROrder ID: 0901126016222021-22-09-2022

The Tribunal noted the partial settlement of dues between the parties and directed the appellant to provide an account statement to the respondent, who is ordered to pay any remaining balance plus agreed interest.

INTERIM_ORDEROrder ID: 0901126016222021-09-03-2022

The Tribunal recorded the respondent-builder's willingness to refund the amount in installments and directed the respondent to clarify the installment schedule, while noting the appellant's preference for receiving principal and interest in separate installment structures.