up_reraStatus: Completed
CASE ID: 0901126014002022

Appellant / Complainant

Jagdeep Singhal Son Of Ram Autar Singhal, Jagdeep Singhal

VS

Respondent

Ansal Properties & Infrastructure Limited

Developer Firm

ansal properties & infrastructure limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

13 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126014002022 by Jagdeep Singhal Son Of Ram Autar Singhal, Jagdeep Singhal against Ansal Properties & Infrastructure Limited before up_rera.

2
Stage 120/02/2023

Exchange of pleadings

The appellant filed an application to withdraw the appeal, which the Tribunal granted, resulting in the case being dismissed as withdrawn.

3
Stage 218/01/2023

Exchange of pleadings

No text available.

4
Stage 313/12/2022

Exchange of pleadings

No text available.

5
Stage 417/11/2022

Exchange of pleadings

The Tribunal granted an adjournment requested by the respondent's counsel and directed the appellant to file a replication/rejoinder before the next hearing date on 13.12.2022.

6
Stage 520/10/2022

Exchange of pleadings

The Tribunal granted adjournment applications filed by both parties and rescheduled the hearing for November 17, 2022.

7
Stage 616/09/2022

Hearing

The Tribunal granted the appellant a final opportunity to file a replication/rejoinder against the respondent's reply and scheduled the defective appeal for hearing on 20.10.2022.

8
Stage 725/08/2022

Hearing

The Tribunal directed the respondent to provide a soft copy of their objections via email to the applicant and counsel within 24 hours, with the applicant permitted to file a reply within one week.

9
Stage 825/07/2022

Hearing

The Tribunal directed the Registry to convert the defective appeal into a regular appeal and established a timeline for the respondent to file objections and the appellant to file a reply.

10
Stage 901/07/2022

Notice

The Tribunal deemed service on the respondent sufficient and granted them a final 10-day extension to file objections, warning that the matter may proceed ex-parte if they fail to appear or respond.

11
Stage 1026/05/2022

Notice

No text available.

12
Stage 1129/04/2022

Defect Removal

The Tribunal issued notice to the respondent and directed the appellant to rectify registry defects and serve the appeal documents via speed-post and email by May 26, 2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Namit Mishra

Respondent Advocate(s)

  • Saurabh Misra
TathyaGrid RERA Intelligence AI