Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126062352021 by Shalini Gupta against Ansal Properties & Infrastructure Limited before up_rera.

2
Stage 126/09/2022

Hearing

The appellant requested to withdraw the appeal, and with no objection from the respondent, the court dismissed the appeal as withdrawn.

3
Stage 230/08/2022

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to personal reasons and scheduled the hearing for 26.09.2022.

4
Stage 303/08/2022

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel on personal grounds and scheduled the appeal for a hearing on 30.08.2022.

5
Stage 415/07/2022

Hearing

The Tribunal has granted a request by the appellant's counsel to reschedule the hearing of Appeal-999/2021 to 03.08.2022.

6
Stage 525/05/2022

Delay condonation

The Tribunal condoned the delay in filing the appeal, noting that the delay was covered by the Supreme Court's Suo Moto orders regarding limitation extensions, and directed the Registry to convert the defective appeal into a regular one.

7
Stage 610/05/2022

Delay condonation

The Tribunal noted that pleadings have been exchanged and rescheduled the hearing for consideration of the application for condonation of delay to 25.05.2022.

8
Stage 722/04/2022

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and directed that the reply be served via email after being uploaded to the e-portal. The defective appeal is scheduled for hearing on 10.05.2022 regarding the condonation of delay.

9
Stage 831/03/2022

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and directed the matter to be listed on 22.04.2022 for consideration of the condonation of delay application.

10
Stage 908/03/2022

Notice

The Tribunal granted the respondent two weeks to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent deadline for the appellant's reply. The matter is scheduled for hearing on 31.03.2022.

11
Stage 1004/01/2022

Delay condonation

The Tribunal issued notice to the respondent regarding the appeal and scheduled the matter for January 25, 2022, to address the application concerning the delay in filing (limitation application).

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey

Respondent Advocate(s)

  • Saurabh Misra
  • Krishna Kumar Singh
TathyaGrid RERA Intelligence AI

Need to research all rulings for ansal properties & infrastructure limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →