up_reraStatus: Completed
CASE ID: 0901126032532022

Appellant / Complainant

Sarjeet Singh

VS

Respondent

Ansal Properties & Infrastructure Limited

Developer Firm

ansal properties & infrastructure limited

Disputed Amount

12,15,163

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional MisrepresentationUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

14 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126032532022 by Sarjeet Singh against Ansal Properties & Infrastructure Limited before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional MisrepresentationUnfair Cancellation & Forfeiture
2
Stage 116/12/2024

Hearing

The Tribunal set aside the Regulatory Authority's order, ruling that the appellant is entitled to a full refund of Rs. 12,15,163 plus interest (MCLR+1%) due to project delays and unfair trade practices by the respondent.

3
Stage 228/11/2024

Hearing

No text available.

4
Stage 323/10/2024

Hearing

The Tribunal granted a request to list the appeal for hearing on 28.11.2024.

5
Stage 402/12/2022

Exchange of pleadings

The Tribunal ordered the case file to be kept in abeyance due to a moratorium issued by the NCLT on November 16, 2022.

6
Stage 509/11/2022

Exchange of pleadings

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the matter for hearing on 02.12.2022.

7
Stage 610/10/2022

Exchange of pleadings

The Tribunal granted the appellant permission to file a replication/rejoinder to the respondent's reply and scheduled the next hearing for November 9, 2022.

8
Stage 705/09/2022

Hearing

The Tribunal noted the absence of the appellant and directed the respondent's counsel to file a reply to the memo of appeal and serve a copy to the appellant via email before the next hearing on 10.10.2022.

9
Stage 804/08/2022

Hearing

The Tribunal granted the respondent ten days to file objections to the grounds of appeal and directed the parties to exchange replies and upload documents to the e-portal before the next hearing on 05.09.2022.

10
Stage 907/07/2022

Defect Removal

The Tribunal directed the Registry to convert the defective appeal into a regular appeal and ordered that notice be issued to the respondent for the hearing scheduled on 04.08.2022.

11
Stage 1030/06/2022

Defect Removal

The Tribunal granted the appellant three days to rectify procedural defects in the appeal and scheduled the matter for hearing on July 7, 2022.

12
Stage 11Final Ruling Order

Tribunal Order #0901126032532022-16-12-2024

The Tribunal set aside the Regulatory Authority's order, ruling that the appellant is entitled to a full refund of Rs. 12,15,163 plus interest (MCLR+1%) due to project delays and unfair trade practices by the respondent.

13
Stage 12Interim Order

Tribunal Order #0901126032532022-02-12-2022

The Tribunal ordered the case file to be kept in abeyance due to a moratorium issued by the NCLT on November 16, 2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order, ruling that the appellant is entitled to a full refund of Rs. 12,15,163 plus interest (MCLR+1%) due to project delays and unfair trade practices by the respondent. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order, ruling that the appellant is entitled to a full refund of Rs. 12,15,163 plus interest (MCLR+1%) due to project delays and unfair trade practices by the respondent.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

on every month delay till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 12Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rishi Saxena

Respondent Advocate(s)

  • Saurabh Misra

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126032532022-16-12-2024

The Tribunal set aside the Regulatory Authority's order, ruling that the appellant is entitled to a full refund of Rs. 12,15,163 plus interest (MCLR+1%) due to project delays and unfair trade practices by the respondent.

INTERIM_ORDEROrder ID: 0901126032532022-02-12-2022

The Tribunal ordered the case file to be kept in abeyance due to a moratorium issued by the NCLT on November 16, 2022.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ansal properties & infrastructure limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →